- A
The project is under budget and behind schedule
Why wrong: CV is negative, so not under budget; there is no schedule information.
- B
The project is over budget
Negative CV and CPI<1 both indicate the project is over budget.
- C
The project is ahead of schedule
Why wrong: CV and CPI measure cost, not schedule.
- D
The project is under budget
Why wrong: A negative CV indicates over budget, not under.
Quick Answer
The answer is that the project is over budget. A negative cost variance of -$5,000 means the actual cost exceeds the earned value by that amount, while a cost performance index of 0.9 confirms that for every dollar spent, only $0.90 of work is being earned—both metrics clearly indicate a cost overrun. On the CompTIA Project+ PK0-005 exam, interpreting cost variance and cost performance index together tests your ability to read project health from earned value management data; a common trap is confusing a negative CV with being behind schedule, but remember CV and CPI only measure cost efficiency, not time. A positive CV or CPI above 1.0 means under budget, while negative or below 1.0 means over budget. Memory tip: think of CPI as a “cents-per-dollar” gauge—if you’re only getting 90 cents back for every dollar spent, you’re losing money.
PK0-005 Project Management Concepts Practice Question
This PK0-005 practice question tests your understanding of project management concepts. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
A project manager calculates the cost variance (CV) as -$5,000 and the cost performance index (CPI) as 0.9. What does this indicate about the project?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
The project is over budget
A negative cost variance (CV) of -$5,000 means the project has spent $5,000 more than the value of work performed, indicating a cost overrun. A cost performance index (CPI) of 0.9 confirms that for every dollar spent, only $0.90 of earned value is being received, which is a clear sign of being over budget. Therefore, the project is over budget, making option B correct.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
The project is under budget and behind schedule
Why it's wrong here
CV is negative, so not under budget; there is no schedule information.
- ✓
The project is over budget
Why this is correct
Negative CV and CPI<1 both indicate the project is over budget.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
The project is ahead of schedule
Why it's wrong here
CV and CPI measure cost, not schedule.
- ✗
The project is under budget
Why it's wrong here
A negative CV indicates over budget, not under.
Common exam traps
Common exam trap: answer the scenario, not the keyword
The trap here is that candidates confuse cost performance metrics (CV, CPI) with schedule performance metrics (SV, SPI), leading them to incorrectly infer schedule status from cost data alone.
Detailed technical explanation
How to think about this question
Earned Value Management (EVM) uses CV = EV - AC and CPI = EV / AC; a negative CV and CPI < 1.0 both signal cost overruns. In practice, a CPI of 0.9 means the project is 10% less efficient in cost than planned, which could trigger corrective actions like re-estimating costs or reducing scope. Real-world scenarios often require combining CPI with TCPI (To-Complete Performance Index) to forecast the efficiency needed for remaining work to stay within budget.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PK0-005 exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
Project Management Concepts — study guide chapter
Learn the concepts, then practise the questions
- →
Project Management Concepts practice questions
Targeted practice on this topic area only
- →
All PK0-005 questions
500 questions across all exam domains
- →
CompTIA Project+ PK0-005 study guide
Full concept coverage aligned to exam objectives
- →
PK0-005 practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PK0-005 practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Project Life Cycle Phases practice questions
Practise PK0-005 questions linked to Project Life Cycle Phases.
Basics of IT Infrastructure and IT Project Management practice questions
Practise PK0-005 questions linked to Basics of IT Infrastructure and IT Project Management.
Project Management Concepts practice questions
Practise PK0-005 questions linked to Project Management Concepts.
Tools and Documentation practice questions
Practise PK0-005 questions linked to Tools and Documentation.
PK0-005 fundamentals practice questions
Practise PK0-005 questions linked to PK0-005 fundamentals.
PK0-005 scenario practice questions
Practise PK0-005 questions linked to PK0-005 scenario.
PK0-005 troubleshooting practice questions
Practise PK0-005 questions linked to PK0-005 troubleshooting.
Practice this exam
Start a free PK0-005 practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PK0-005 question test?
Project Management Concepts — This question tests Project Management Concepts — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: The project is over budget — A negative cost variance (CV) of -$5,000 means the project has spent $5,000 more than the value of work performed, indicating a cost overrun. A cost performance index (CPI) of 0.9 confirms that for every dollar spent, only $0.90 of earned value is being received, which is a clear sign of being over budget. Therefore, the project is over budget, making option B correct.
What should I do if I get this PK0-005 question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Last reviewed: Jun 24, 2026
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.