Question 399 of 500
Project Management ConceptshardMultiple ChoiceObjective-mapped

Quick Answer

The answer is -$50,000. This cost variance (CV) calculation is derived from the earned value management formula CV = EV minus AC, where EV is the earned value of work performed and AC is the actual cost incurred. Since the project is 40% complete against a $500,000 budget, the EV is $200,000, and with an AC of $250,000, the resulting negative CV of -$50,000 signals the project is over budget. On the CompTIA Project+ PK0-005 exam, this tests your ability to apply earned value formulas to real project data, often appearing in scenario-based questions where you must first compute EV from the percentage complete. A common trap is confusing EV with planned value (PV) or forgetting to multiply the budget by the completion percentage. To remember the formula, think of the mnemonic “CV = EV minus AC: if the answer is negative, your costs are excessive.”

PK0-005 Project Management Concepts Practice Question

This PK0-005 practice question tests your understanding of project management concepts. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A project has a budget of $500,000 and is 40% complete. The actual cost incurred is $250,000. What is the cost variance?

Question 1hardmultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

-$50,000

Cost variance (CV) is calculated as Earned Value (EV) minus Actual Cost (AC). EV is 40% of the $500,000 budget, which equals $200,000. AC is $250,000, so CV = $200,000 - $250,000 = -$50,000. A negative CV indicates the project is over budget.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • -$50,000

    Why this is correct

    Correct. CV = EV - AC = 200k - 250k = -50k.

    Related concept

    Read the scenario before looking for a memorised answer.

  • -$20,000

    Why it's wrong here

    Incorrect calculation.

  • $20,000

    Why it's wrong here

    Incorrect calculation.

  • $50,000

    Why it's wrong here

    This would be positive, but actual cost exceeds earned value.

Common exam traps

Common exam trap: answer the scenario, not the keyword

CompTIA often tests the direction of the variance sign, tricking candidates into thinking a positive variance is always good, but here the actual cost exceeds earned value, so the correct variance is negative.

Detailed technical explanation

How to think about this question

Earned Value Management (EVM) uses CV to measure cost performance against the planned budget. The formula CV = EV - AC is defined in PMI's PMBOK Guide. A negative CV means the project has spent more than the value of work performed, triggering corrective action. Real-world scenarios often involve tracking CV at regular intervals to forecast Estimate at Completion (EAC) using formulas like EAC = BAC / CPI, where CPI = EV / AC.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PK0-005 exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PK0-005 practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PK0-005 practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PK0-005 question test?

Project Management Concepts — This question tests Project Management Concepts — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: -$50,000 — Cost variance (CV) is calculated as Earned Value (EV) minus Actual Cost (AC). EV is 40% of the $500,000 budget, which equals $200,000. AC is $250,000, so CV = $200,000 - $250,000 = -$50,000. A negative CV indicates the project is over budget.

What should I do if I get this PK0-005 question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Keep practising

More PK0-005 practice questions

Last reviewed: Jun 30, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.