- A
Conduct a meeting with stakeholders to discuss the impact of the change.
Why wrong: The impact should have been assessed before approval; now the change is approved and must be implemented.
- B
Update the project management plan and baseline to reflect the approved change.
The PM must adjust plans and baselines to incorporate the change and keep the project aligned.
- C
Defer the change to the next project phase to minimize disruption.
Why wrong: Approved changes should be implemented as planned; deferring may cause issues.
- D
Inform the development team to continue with the original scope and ignore the change.
Why wrong: Approved changes must be incorporated; ignoring them violates the change control process.
Quick Answer
The answer is to update the project management plan and baselines to reflect the approved change. This is correct because the change control board’s approval authorizes the project manager to formally integrate the new feature into the project’s control processes; updating the scope, schedule, and cost baselines ensures that performance measurement and future work align with the revised plan. On the CompTIA Project+ PK0-005 exam, this tests your understanding of the post-CCB approval workflow, often appearing as a trap where candidates mistakenly think the next step is to implement the change immediately or inform the team first. The key is that documentation and baseline updates must precede execution to maintain project integrity. Remember the mnemonic “Plan Before Action” — after CCB approval, always update the plan and baselines before moving forward.
PK0-005 Project Life Cycle Phases Practice Question
This PK0-005 practice question tests your understanding of project life cycle phases. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
A project is in the execution phase, and the project manager receives a change request to add a new feature that is not in the scope statement. The change request has been approved by the change control board. What must the project manager do next?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Update the project management plan and baseline to reflect the approved change.
Once the change control board (CCB) approves a change request, the project manager must formally integrate the approved change into the project by updating the project management plan and the associated baselines (scope, schedule, cost). This ensures that all future project work, performance measurement, and reporting are aligned with the new approved scope, maintaining the integrity of the project's control processes as defined in the PMBOK Guide.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Conduct a meeting with stakeholders to discuss the impact of the change.
Why it's wrong here
The impact should have been assessed before approval; now the change is approved and must be implemented.
- ✓
Update the project management plan and baseline to reflect the approved change.
Why this is correct
The PM must adjust plans and baselines to incorporate the change and keep the project aligned.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Defer the change to the next project phase to minimize disruption.
Why it's wrong here
Approved changes should be implemented as planned; deferring may cause issues.
- ✗
Inform the development team to continue with the original scope and ignore the change.
Why it's wrong here
Approved changes must be incorporated; ignoring them violates the change control process.
Common exam traps
Common exam trap: answer the scenario, not the keyword
The trap here is that candidates often confuse the sequence of the change control process, thinking a stakeholder meeting to discuss impact is still needed after CCB approval, when in fact the approval itself confirms the impact has been accepted and the next step is to update the plan and baselines.
Detailed technical explanation
How to think about this question
In project management, baselines (scope, schedule, cost) are the formal, approved versions of the project plan against which performance is measured using earned value management (EVM). Updating the baseline after a CCB-approved change ensures that the project's performance measurement baseline (PMB) remains valid, allowing accurate calculation of metrics like SPI and CPI. A real-world scenario is a software project where a new feature is approved mid-sprint; the project manager must update the scope baseline and adjust the work breakdown structure (WBS) to reflect the new deliverables, then communicate the revised schedule and budget to the team.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PK0-005 exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
Project Life Cycle Phases — study guide chapter
Learn the concepts, then practise the questions
- →
Project Life Cycle Phases practice questions
Targeted practice on this topic area only
- →
All PK0-005 questions
500 questions across all exam domains
- →
CompTIA Project+ PK0-005 study guide
Full concept coverage aligned to exam objectives
- →
PK0-005 practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PK0-005 practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Project Life Cycle Phases practice questions
Practise PK0-005 questions linked to Project Life Cycle Phases.
Basics of IT Infrastructure and IT Project Management practice questions
Practise PK0-005 questions linked to Basics of IT Infrastructure and IT Project Management.
Project Management Concepts practice questions
Practise PK0-005 questions linked to Project Management Concepts.
Tools and Documentation practice questions
Practise PK0-005 questions linked to Tools and Documentation.
PK0-005 fundamentals practice questions
Practise PK0-005 questions linked to PK0-005 fundamentals.
PK0-005 scenario practice questions
Practise PK0-005 questions linked to PK0-005 scenario.
PK0-005 troubleshooting practice questions
Practise PK0-005 questions linked to PK0-005 troubleshooting.
Practice this exam
Start a free PK0-005 practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PK0-005 question test?
Project Life Cycle Phases — This question tests Project Life Cycle Phases — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Update the project management plan and baseline to reflect the approved change. — Once the change control board (CCB) approves a change request, the project manager must formally integrate the approved change into the project by updating the project management plan and the associated baselines (scope, schedule, cost). This ensures that all future project work, performance measurement, and reporting are aligned with the new approved scope, maintaining the integrity of the project's control processes as defined in the PMBOK Guide.
What should I do if I get this PK0-005 question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Last reviewed: Jun 11, 2026
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.