- A
Critical path method
Why wrong: A scheduling method, not an estimating technique.
- B
Parametric estimating
Uses historical data and statistical relationships.
- C
Three-point estimating
Uses optimistic, pessimistic, and most likely estimates.
- D
Monte Carlo simulation
Why wrong: A simulation technique, not a basic estimating technique.
- E
Analogous estimating
Why wrong: Also a technique, but not part of the two correct ones here.
Quick Answer
The answer is three-point estimating and parametric estimating. Three-point estimating is correct because it accounts for uncertainty by calculating an average using optimistic, pessimistic, and most likely durations, often refined with a weighted formula like PERT. Parametric estimating is the other correct technique, as it uses historical data and statistical relationships—such as cost per square meter or hours per unit—to produce objective, data-driven duration estimates based on measurable parameters. On the CompTIA Project+ PK0-005 exam, this question tests your ability to distinguish standard estimating techniques from less common or non-standard options; a common trap is confusing analogous estimating (which uses whole-project history) with parametric estimating (which uses unit-level parameters). Remember the memory tip: “Three points for uncertainty, parameters for precision”—if you see a formula involving optimistic, pessimistic, and most likely, it’s three-point; if you see a rate like hours per task, it’s parametric.
PK0-005 Project Management Concepts Practice Question
This PK0-005 practice question tests your understanding of project management concepts. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
A project manager is developing a project schedule and needs to estimate activity durations. Which TWO techniques are commonly used for estimating activity durations? (Choose two.)
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Parametric estimating
Parametric estimating (B) uses historical data and statistical relationships between variables (e.g., cost per square meter, hours per unit) to calculate activity durations. It is a standard technique in project schedule development because it provides objective, data-driven estimates based on measurable parameters.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Critical path method
Why it's wrong here
A scheduling method, not an estimating technique.
- ✓
Parametric estimating
Why this is correct
Uses historical data and statistical relationships.
Related concept
Read the scenario before looking for a memorised answer.
- ✓
Three-point estimating
Why this is correct
Uses optimistic, pessimistic, and most likely estimates.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Monte Carlo simulation
Why it's wrong here
A simulation technique, not a basic estimating technique.
- ✗
Analogous estimating
Why it's wrong here
Also a technique, but not part of the two correct ones here.
Common exam traps
Common exam trap: answer the scenario, not the keyword
CompTIA often tests the distinction between techniques used for estimating durations (parametric, three-point) versus techniques used for schedule analysis (critical path method, Monte Carlo simulation), leading candidates to confuse CPM with an estimation method.
Detailed technical explanation
How to think about this question
Parametric estimating multiplies a unit rate (e.g., 10 hours per line of code) by the quantity of work (e.g., 500 lines) to produce a duration estimate. Three-point estimating (C) uses optimistic (O), most likely (M), and pessimistic (P) values to calculate a weighted average (often via PERT: (O+4M+P)/6), which accounts for uncertainty and risk in each activity. Both techniques are defined in the PMBOK Guide under the 'Estimate Activity Durations' process.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
Project Management Concepts — study guide chapter
Learn the concepts, then practise the questions
- →
Project Management Concepts practice questions
Targeted practice on this topic area only
- →
All PK0-005 questions
500 questions across all exam domains
- →
CompTIA Project+ PK0-005 study guide
Full concept coverage aligned to exam objectives
- →
PK0-005 practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PK0-005 practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Project Life Cycle Phases practice questions
Practise PK0-005 questions linked to Project Life Cycle Phases.
Basics of IT Infrastructure and IT Project Management practice questions
Practise PK0-005 questions linked to Basics of IT Infrastructure and IT Project Management.
Project Management Concepts practice questions
Practise PK0-005 questions linked to Project Management Concepts.
Tools and Documentation practice questions
Practise PK0-005 questions linked to Tools and Documentation.
PK0-005 fundamentals practice questions
Practise PK0-005 questions linked to PK0-005 fundamentals.
PK0-005 scenario practice questions
Practise PK0-005 questions linked to PK0-005 scenario.
PK0-005 troubleshooting practice questions
Practise PK0-005 questions linked to PK0-005 troubleshooting.
Practice this exam
Start a free PK0-005 practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PK0-005 question test?
Project Management Concepts — This question tests Project Management Concepts — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Parametric estimating — Parametric estimating (B) uses historical data and statistical relationships between variables (e.g., cost per square meter, hours per unit) to calculate activity durations. It is a standard technique in project schedule development because it provides objective, data-driven estimates based on measurable parameters.
What should I do if I get this PK0-005 question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Last reviewed: Jun 30, 2026
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.