Which process provides the Project Board with the mechanism to authorize a project's initiation?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Directing a Project
Directing a Project includes the activity 'Authorizing initiation', where the Project Board reviews the SU outputs and authorizes IP.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Starting up a Project
Why it's wrong here
Starting up a Project requests authorization but does not grant it.
- ✓
Directing a Project
Why this is correct
DP contains the specific board authorization activities, including authorizing initiation.
- ✗
Controlling a Stage
Why it's wrong here
Controlling a Stage manages delivery stages.
- ✗
Initiating a Project
Why it's wrong here
Initiating a Project is executed by the Project Manager, not authorized by them.
About these practice questions
This PRINCE2-PRACTITIONER question is part of Courseiva's 297-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official AXELOS / PeopleCert exam blueprint
This PRINCE2-PRACTITIONER practice question is part of Courseiva's free AXELOS / PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2-PRACTITIONER exam.