PK0-005 Tools and Documentation • Set 9
PK0-005 Tools and Documentation Practice Test 9 — 15 questions with explanations. Free, no signup.
A project has a budget at completion (BAC) of $200,000. After 3 months, the earned value (EV) is $80,000, and the actual cost (AC) is $100,000. What is the estimate at completion (EAC) assuming the cost performance index (CPI) will remain the same for the remainder of the project?
Choose an answer to begin — your selection is scored in the full session.
15 questions · instant feedback and full explanations after every question.