A project has a budget at completion (BAC) of $200,000. The earned value (EV) is $100,000, actual cost (AC) is $120,000, and planned value (PV) is $90,000. What is the estimate at completion (EAC) if the project will continue to perform at the current cost performance index (CPI)?