In a network diagram, Activity A has early start (ES) of 0 and early finish (EF) of 5. Activity B depends on A and has ES=5, EF=10. Activity C also depends on A and has ES=5, EF=12. Activity D depends on B and C and has ES=12, EF=15. What is the total float for Activity C?