You are the project manager for a software upgrade project at a mid-sized company. The project has a budget of $500,000 and a timeline of 12 months. The team consists of 10 members, including developers, testers, and a business analyst. The project is in month 8, and the team has completed 60% of the work but has spent $400,000. The sponsor is concerned about the budget overrun and asks for a recovery plan. The original estimate at completion (EAC) was $500,000. Using earned value management, you calculate the cost performance index (CPI) is 0.75 and the schedule performance index (SPI) is 0.90. The team is demoralized due to scope creep and unclear requirements. The business analyst recently left, and the replacement is not yet fully onboarded. Which of the following is the BEST course of action to bring the project back on track?