A government IT project is being managed using a predictive lifecycle. The project must comply with numerous regulatory standards, including data privacy and security. The project manager developed a comprehensive quality management plan that includes regular quality audits by an independent team. At the first milestone quality audit, the auditor identifies three non-conformances related to documentation and testing procedures. The project manager is under pressure from the sponsor to stay on schedule. The project manager needs to address the non-conformances effectively while minimizing schedule impact.