During the Sprint Planning event, the Development Team realizes they have pulled in significantly more Product Backlog items than their historical velocity supports. What is the most appropriate action according to Scrum principles?
Sprint Planning is a collaborative negotiation where the Development Team forecasts what can be delivered based on past performance and current capacity. Adjusting the scope early guarantees that the resulting Sprint Goal remains achievable and maintains team accountability.
Why this answer
Scrum relies on transparency and realistic forecasting to establish a sustainable cadence. The Development Team must collaborate immediately with the Product Owner to right-size the Sprint Backlog before finalizing the plan. This ensures the team commits only to work they can realistically complete, maintaining predictability and avoiding burnout.
Exam trap
Candidates often think the Development Team must work overtime or simply lower their quality standards to complete an overcommitted forecast, rather than negotiating capacity directly with the Product Owner.