CSM Scrum Team Roles and Accountabilities Practice Question

During Sprint Planning, the Product Owner demands that the Development Team commit to a specific set of items to meet a quarterly company milestone. What is the most appropriate action for the Scrum Master?

⚠ Common exam trap

Many candidates believe the Product Owner or management can force a commitment to meet external milestones, ignoring that the Development Team forecasts its own capacity.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Educate both parties that the Development Team forecasts its capacity and pulls work iteratively.

The Scrum Master must protect the integrity of the Scrum framework by clarifying that the Development Team alone estimates and pulls work. Product Owners manage value, not capacity. This distinction matters because forcing arbitrary commitments destroys morale and distorts forecasting metrics.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Support the Product Owner by enforcing the quarterly milestone as a binding team commitment.

    Why it's wrong here

    Enforcing a milestone as a binding commitment converts the Sprint Goal into a fixed-scope contract, contradicting empiricism; the Development Team forecasts, it does not commit to scope. It tempts because Product Owners legitimately own value ordering and stakeholder deadlines, but that authority covers backlog priority, not compelling a forecast.

  • ✓

    Educate both parties that the Development Team forecasts its capacity and pulls work iteratively.

    Why this is correct

    The Scrum Master acts as a coach to ensure all roles understand their boundaries within the framework. Clarifying that the team creates a forecast rather than a rigid commitment preserves sustainable pacing and genuine accountability.

  • ✗

    Realign the Product Backlog items into smaller tasks so the team can absorb the extra pressure.

    Why it's wrong here

    Splitting backlog items into smaller tasks does not change the team's capacity, so it cannot absorb the demanded scope; it merely disguises an overloaded Sprint Backlog. Decomposition is genuinely useful for refining large items into estimable, transparent work, but it is not a mechanism for meeting externally imposed pressure.

  • ✗

    Take over Sprint Planning facilitation and unilaterally assign tasks to balance the workload.

    Why it's wrong here

    Unilateral task assignment by the Scrum Master removes the Development Team's self-management, which Sprint Planning exists to enable. Facilitation means guiding the event, not dictating work. This would be tempting where a team is genuinely unable to self-organise, but even then the Scrum Master coaches rather than reassigns tasks.

About these practice questions

One of 312 original CSM practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official Scrum Alliance exam blueprint

This CSM practice question is part of Courseiva's free Scrum Alliance certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CSM exam.