CSM Scrum Master Core Competencies Practice Question
A Scrum Master notices that the team has been consistently failing to meet their Sprint Goal for three consecutive Sprints. What is the most appropriate first step to take?
⚠ Common exam trap
Candidates often choose to immediately step in and solve the problem for the team or report the failure directly to management, violating the Scrum Master's role as a facilitator of self-management.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Bring up the observations at the next Sprint Retrospective to encourage inspection.
The Scrum Master must facilitate a conversation to uncover the root cause of the failure. By observing the team and encouraging them to inspect their process, the Scrum Master helps them identify systemic issues. This is a crucial diagnostic step that respects team autonomy while fulfilling the Scrum Master's duty to improve the team's effectiveness and agility through empirical process control.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Change the team members to improve performance.
Why it's wrong here
Changing team members is a drastic measure that rarely addresses systemic process issues. It disrupts team dynamics and ignores the potential that current problems are caused by external factors or organizational impediments. The Scrum Master should focus on improving the team environment and process before considering personnel changes.
- ✓
Bring up the observations at the next Sprint Retrospective to encourage inspection.
Why this is correct
The Retrospective is the dedicated event for the team to inspect their process and create a plan for improvement. By bringing the observation to the team, the Scrum Master triggers an honest, evidence-based discussion, allowing the team to identify why they are failing and how to adapt accordingly.
- ✗
Report the failure to the team's functional manager.
Why it's wrong here
Reporting to a functional manager is an escalation that undermines the team's self-management and psychological safety. It suggests the team cannot solve their own problems. The Scrum Master's role is to support the team internally, not to act as a whistleblower or disciplinary agent for the functional leadership.
- ✗
Reduce the team's velocity for the next Sprint.
Why it's wrong here
Arbitrarily reducing velocity ignores the underlying issues that are causing the failure. While it might lead to 'meeting' the Sprint Goal, it doesn't solve the root cause. The team needs to analyze their process constraints, not just adjust their capacity expectations to fit an broken system.
About these practice questions
This CSM question is part of Courseiva's 312-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed September 2026 · checked against the official Scrum Alliance exam blueprint
This CSM practice question is part of Courseiva's free Scrum Alliance certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CSM exam.