PMP Practice Question: Business Environment: strategy and project benefits
Your project is 40% complete and running 15% over budget due to unforeseen technical challenges. The project sponsor suggests reducing scope by removing non-essential features to meet the budget. What should you do?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Analyze the impact of the proposed reduction and submit a change request to the CCB
The project manager should follow the formal change control process to evaluate the impact of reducing scope and obtain approval from the change control board (CCB) before making changes.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Update the project charter to reflect the new scope without further approval
Why it's wrong here
The Project Charter is a high-level document authorizing the project and signed by the project sponsor or an authorized body. A Project Manager lacks the authority to unilaterally update the project charter, particularly to reflect significant scope changes. Such modifications require formal approval from the sponsor or governing body, as the charter establishes the project's initial intent and boundaries. Furthermore, detailed scope changes are typically managed through the scope baseline, not the charter itself.
- ✗
Reject the sponsor's suggestion because scope reduction always leads to project failure
Why it's wrong here
The statement that scope reduction 'always' leads to project failure is an absolute and incorrect generalization. Scope reduction, or de-scoping, is a legitimate and often necessary strategy for managing project constraints such as budget overruns or schedule delays. When implemented through a controlled change process and with proper stakeholder agreement, it can effectively help bring a troubled project back on track, ensuring the successful delivery of core value and objectives.
- ✗
Agree with the sponsor and immediately instruct the team to stop work on non-essential features
Why it's wrong here
This action bypasses the critical 'Perform Integrated Change Control' process, which is fundamental to project governance. Even if the sponsor suggests it, the Project Manager must not unilaterally implement scope changes without proper analysis and formal approval via a change request. Bypassing the Change Control Board (CCB) or established process can lead to uncontrolled scope creep, rework, and misalignment with project objectives and stakeholder expectations, ultimately jeopardizing project success.
- ✓
Analyze the impact of the proposed reduction and submit a change request to the CCB
Why this is correct
This is the correct PMP approach, demonstrating adherence to the Integrated Change Control process. The Project Manager's initial responsibility is to analyze the potential impact of any proposed scope change on all project constraints, including schedule, cost, quality, resources, and risks. Following this thorough analysis, a formal change request must be submitted to the Change Control Board (CCB) for their review, approval, or rejection, ensuring adherence to the established change control process and maintaining project integrity.
Go deeper
Related to this question
Learn chapter
Introduction to the PMP Exam and Project Management Basics
Key term
Change Control Process
A formal, structured procedure used to manage any changes to a project's scope, schedule, budget, or requirements, ensuring every modification is reviewed, approved, tested, and documented before implementation.
About these practice questions
Courseiva writes every PMP question from scratch — 800 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.