Courseiva

PMP Practice Question: Business Environment: strategy and project benefits

You are the project manager for a government IT project. Midway through, a new regulation is enacted that requires additional data privacy controls. The team estimates this will add 4 weeks to the schedule and increase costs by 10%. What should you do FIRST?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Submit a change request to the change control board to incorporate the required changes

When a new regulation impacts a project, the project manager should follow the formal change control process. The first step is to assess the impact and submit a change request to the change control board (CCB) for review and approval. This ensures compliance while maintaining proper governance. Option A is wrong because implementing changes without approval bypasses change control. Option B is wrong because ignoring regulations exposes the organization to legal risk. Option C is wrong because stopping the project is an extreme measure that should only be considered after evaluating alternatives.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Instruct the team to start implementing the new controls immediately

    Why it's wrong here

    As a project manager, instructing the team to implement new controls immediately without formal approval constitutes an unauthorized change. This action bypasses established change control processes and project governance, potentially impacting project baselines (scope, schedule, cost) without proper assessment or stakeholder consensus. Such unilateral decisions can lead to scope creep, rework, and non-compliance with organizational policies.

  • Ignore the regulation until the project is complete to avoid delays

    Why it's wrong here

    Ignoring a newly issued government regulation until project completion is a severe breach of professional responsibility and ethical conduct. Regulatory compliance is mandatory, and failing to address it exposes the organization to significant legal penalties, financial fines, reputational damage, and potential project cancellation. The project manager has a fiduciary duty to ensure the project adheres to all applicable laws and regulations.

  • Recommend stopping the project until the regulation is clarified

    Why it's wrong here

    Recommending to stop the project entirely due to a new regulation is an extreme and premature response. Before resorting to such a drastic measure, the project manager should first assess the regulation's specific impact, explore potential solutions, and propose a path forward. A temporary pause or re-scoping through formal change control is a more appropriate initial step than outright cessation, which incurs significant costs and delays.

  • Submit a change request to the change control board to incorporate the required changes

    Why this is correct

    Submitting a change request to the Change Control Board (CCB) is the correct and most professional course of action. This formal process ensures that the mandatory regulatory changes are properly assessed for their impact on project baselines, resources, and risks. The CCB then reviews, approves, or rejects the proposed changes, ensuring integrated change control and maintaining project governance and stakeholder alignment.

About these practice questions

This PMP question is part of Courseiva's 800-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.