- A
Recommend increasing resources for Project B to get it back on track
Why wrong: This is a specific solution that may not be appropriate without considering portfolio balance.
- B
Present the status and strategic alignment of each project to the committee and facilitate a decision
The PM should provide data and analysis to support the committee's decision-making process.
- C
Recommend stopping Project C and reallocating resources to Project B
Why wrong: The decision should be made by the steering committee; the PM provides analysis, not unilateral recommendations.
- D
Ask each project manager to submit a recovery plan and then decide
Why wrong: While recovery plans are useful, the PM should first provide an overall portfolio analysis to the committee.
Quick Answer
The answer is to present the status and strategic alignment of each project to the steering committee and facilitate a decision. This is correct because portfolio prioritization relies on strategic alignment as the primary driver, and the project manager’s role is to provide objective data—not to unilaterally override governance. The steering committee holds the authority to balance trade-offs between schedule performance and shifting market value, making their informed decision essential for maintaining portfolio health. On the PMP exam, this scenario tests your understanding of the portfolio governance framework and the distinction between a project manager’s analytical duties versus the committee’s decision-making power. A common trap is assuming the PM should prioritize based on schedule alone or personal bias; instead, remember that strategic alignment must be continuously validated against current business conditions. Memory tip: “Present, don’t prescribe”—your job is to lay out the facts, not pick the winner.
PMP Practice Question: Business Environment: strategy and project benefits
This PMP practice question tests your understanding of business environment: strategy and project benefits. The scenario asks you to isolate a root cause — eliminate options that address a different problem before choosing. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
You are managing a portfolio of three projects. Project A is on track and aligned with strategic goals. Project B is behind schedule but has high strategic value. Project C is on time but its strategic value has diminished due to market changes. The steering committee asks you to recommend which project to prioritize. What should you do?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Present the status and strategic alignment of each project to the committee and facilitate a decision
Option A is correct because the PM should present an objective analysis of each project's status, strategic alignment, and trade-offs, allowing the committee to make an informed decision. Option B is wrong because the PM should not make the decision alone. Option C is wrong because it is biased and ignores the diminished value of Project C. Option D is wrong because it avoids the issue.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Recommend increasing resources for Project B to get it back on track
Why it's wrong here
This is a specific solution that may not be appropriate without considering portfolio balance.
- ✓
Present the status and strategic alignment of each project to the committee and facilitate a decision
Why this is correct
The PM should provide data and analysis to support the committee's decision-making process.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Recommend stopping Project C and reallocating resources to Project B
Why it's wrong here
The decision should be made by the steering committee; the PM provides analysis, not unilateral recommendations.
- ✗
Ask each project manager to submit a recovery plan and then decide
Why it's wrong here
While recovery plans are useful, the PM should first provide an overall portfolio analysis to the committee.
Common exam traps
Common exam trap: answer the scenario, not the keyword
Many certification questions include familiar terms but test a specific constraint. Read the exact wording before choosing an answer that is generally true but wrong for this case.
Detailed technical explanation
How to think about this question
This question should be treated as a scenario, not a definition check. Identify the problem, the constraint and the best action. Then compare each option against those facts.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
- Use explanations to understand the rule behind the answer.
TExam Day Tips
- Underline the problem statement mentally.
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which PMP exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.
- →
Business Environment: strategy and project benefits — study guide chapter
Learn the concepts, then practise the questions
- →
Business Environment: strategy and project benefits practice questions
Targeted practice on this topic area only
- →
All PMP questions
892 questions across all exam domains
- →
Project Management Professional PMP study guide
Full concept coverage aligned to exam objectives
- →
PMP practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PMP practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
People — Leading Projects practice questions
Practise PMP questions linked to People — Leading Projects.
Process — Managing Technical Aspects practice questions
Practise PMP questions linked to Process — Managing Technical Aspects.
Business Environment — Strategy and Value practice questions
Practise PMP questions linked to Business Environment — Strategy and Value.
Business Environment: strategy and project benefits practice questions
Practise PMP questions linked to Business Environment: strategy and project benefits.
PMP fundamentals practice questions
Practise PMP questions linked to PMP fundamentals.
PMP scenario practice questions
Practise PMP questions linked to PMP scenario.
PMP troubleshooting practice questions
Practise PMP questions linked to PMP troubleshooting.
Practice this exam
Start a free PMP practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PMP question test?
Business Environment: strategy and project benefits — This question tests Business Environment: strategy and project benefits — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Present the status and strategic alignment of each project to the committee and facilitate a decision — Option A is correct because the PM should present an objective analysis of each project's status, strategic alignment, and trade-offs, allowing the committee to make an informed decision. Option B is wrong because the PM should not make the decision alone. Option C is wrong because it is biased and ignores the diminished value of Project C. Option D is wrong because it avoids the issue.
What should I do if I get this PMP question wrong?
Identify which PMP exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Last reviewed: Jun 21, 2026
This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.