Question 766 of 892
Process — Managing Technical AspectshardMultiple SelectObjective-mapped

Quick Answer

The answer is to implement the contingency plan by engaging the alternative vendor, then assess the cost impact to update the cost baseline through change control, and finally communicate the situation to stakeholders. This sequence is correct because a contingency plan is pre-approved for execution when a risk trigger occurs, but any resulting cost impact must be formally integrated into the project budget via the Perform Integrated Change Control process, while transparent communication with stakeholders fulfills the Plan Communications Management requirement. On the PMP exam, this scenario tests your ability to distinguish between executing a planned response and the subsequent need for change management, as a common trap is to skip the cost baseline update or to delay implementation while seeking approval. The search intent keywords—contingency plan implement, cost impact, and communicate stakeholders—are directly embedded in this workflow. Remember the mnemonic ICA: Implement, Cost assess, Announce.

PMP Process — Managing Technical Aspects Practice Question

This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

You are managing a large-scale construction project. A critical vendor has informed you that they will be delayed by two months due to a raw material shortage. This risk was identified and recorded in the risk register with a contingency plan to use an alternative vendor. However, the alternative vendor's materials are more expensive and will increase project costs by 10%. Which THREE actions should you take?

Question 1hardmulti select
Read the full NAT/PAT explanation →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Request a change request to update the cost baseline and budget.

First, implement the contingency plan as it was pre-approved. Then, assess the cost impact to update the cost baseline through change control. Finally, communicate the situation to stakeholders. These steps align with PMI's risk and communication management.

Key principle: NAT direction and interface roles matter as much as the IP address mapping. Inside/outside designation controls which traffic is translated.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Request a change request to update the cost baseline and budget.

    Why this is correct

    The cost increase requires a change request to update the cost baseline through formal change control.

    Related concept

    Static NAT maps one inside address to one outside address.

  • Notify key stakeholders about the situation and the plan to proceed.

    Why this is correct

    Stakeholders should be informed about the risk occurrence and the response being taken.

    Related concept

    Static NAT maps one inside address to one outside address.

  • Instruct the team to work overtime to recover the schedule.

    Why it's wrong here

    Overtime may help schedule but does not address the vendor delay directly and may not be effective.

  • Implement the contingency plan by engaging the alternative vendor.

    Why this is correct

    The contingency plan exists for this risk; implement it as planned.

    Related concept

    Static NAT maps one inside address to one outside address.

  • Reject the vendor's notice and demand they meet the original deadline.

    Why it's wrong here

    Demanding compliance without a viable alternative is unrealistic and may damage the relationship.

Common exam traps

Common exam trap: NAT rules depend on direction and matching traffic

NAT is not only about the public address. The inside/outside interface roles and the ACL or rule that matches traffic are just as important.

Detailed technical explanation

How to think about this question

NAT questions usually test address translation, overload/PAT behaviour, static mappings and whether the right traffic is being translated. Read the interface direction and address terms carefully.

KKey Concepts to Remember

  • Static NAT maps one inside address to one outside address.
  • PAT allows many inside hosts to share one public address using ports.
  • Inside local and inside global describe the private and translated addresses.
  • NAT ACLs identify traffic for translation, not always security filtering.

TExam Day Tips

  • Identify inside and outside interfaces first.
  • Check whether the scenario needs static NAT, dynamic NAT or PAT.
  • Do not confuse NAT matching ACLs with normal packet-filtering intent.

Key takeaway

NAT direction and interface roles matter as much as the IP address mapping. Inside/outside designation controls which traffic is translated.

Real-world example

How this comes up in practice

A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.

What to study next

Got this wrong? Here's your next step.

Review the four NAT address types (inside local, inside global, outside local, outside global), PAT port overload, and static vs dynamic NAT use cases. Then practise related PMP NAT questions on configuration and troubleshooting.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Static NAT maps one inside address to one outside address..

What is the correct answer to this question?

The correct answer is: Request a change request to update the cost baseline and budget. — First, implement the contingency plan as it was pre-approved. Then, assess the cost impact to update the cost baseline through change control. Finally, communicate the situation to stakeholders. These steps align with PMI's risk and communication management.

What should I do if I get this PMP question wrong?

Review the four NAT address types (inside local, inside global, outside local, outside global), PAT port overload, and static vs dynamic NAT use cases. Then practise related PMP NAT questions on configuration and troubleshooting.

What is the key concept behind this question?

Static NAT maps one inside address to one outside address.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 21, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.