- A
Risk budget
The risk budget is part of the risk management plan.
- B
Work breakdown structure
Why wrong: The WBS is an output of scope planning.
- C
Risk management plan
This is the primary output of Plan Risk Management.
- D
Probability and impact matrix
Why wrong: This is a tool/technique, not an output.
- E
Risk register
Why wrong: The risk register is an output of Identify Risks.
Quick Answer
The answer is the Risk Management Plan and the Risk Budget. The Plan Risk Management process establishes how risk activities will be conducted, and its primary output is the Risk Management Plan, which defines the methodology, roles, and timing for risk management. The Risk Budget is also an output because it allocates contingency reserves based on the agreed risk thresholds, ensuring funds are available for planned risk responses. On the PMP exam, this question tests your understanding that the first risk process produces a governance document and a financial reserve, not the risk register or risk responses. A common trap is confusing the Risk Budget with the overall project budget or assuming the risk register is created here. To remember, think of the two outputs as the “how” (the plan) and the “how much” (the budget).
PMP Process — Managing Technical Aspects Practice Question
This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
Which TWO of the following are outputs of the 'Plan Risk Management' process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Risk budget
The 'Plan Risk Management' process is the first step in risk management planning, and its primary output is the Risk Management Plan (Option C). This plan defines how risk management activities will be structured and performed throughout the project. The Risk Budget (Option A) is also an output of this process, as it allocates funds specifically for risk responses, including contingency reserves, based on the agreed risk thresholds and management approach.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Risk budget
Why this is correct
The risk budget is part of the risk management plan.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Work breakdown structure
Why it's wrong here
The WBS is an output of scope planning.
- ✓
Risk management plan
Why this is correct
This is the primary output of Plan Risk Management.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Probability and impact matrix
Why it's wrong here
This is a tool/technique, not an output.
- ✗
Risk register
Why it's wrong here
The risk register is an output of Identify Risks.
Common exam traps
Common exam trap: answer the scenario, not the keyword
The trap here is that candidates confuse the Probability and Impact Matrix (a tool/technique) with an output, or mistake the Risk Register (an output of Identify Risks) as a product of the planning process, because both are closely associated with risk management activities.
Trap categories for this question
Command / output trap
The WBS is an output of scope planning.
Detailed technical explanation
How to think about this question
Under the hood, the Risk Budget is derived from the organization's risk appetite and thresholds, often calculated using expected monetary value (EMV) or Monte Carlo simulations during quantitative analysis, but the budget itself is set during planning to ensure funds are available for future risk responses. The Risk Management Plan includes the methodology, roles, timing, and scoring rules (like the probability and impact matrix), making it the blueprint for all subsequent risk activities. In a real-world scenario, failing to establish a risk budget early can lead to insufficient contingency reserves, causing project delays when risks materialize.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
Process — Managing Technical Aspects — study guide chapter
Learn the concepts, then practise the questions
- →
Process — Managing Technical Aspects practice questions
Targeted practice on this topic area only
- →
All PMP questions
892 questions across all exam domains
- →
Project Management Professional PMP study guide
Full concept coverage aligned to exam objectives
- →
PMP practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PMP practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
People — Leading Projects practice questions
Practise PMP questions linked to People — Leading Projects.
Process — Managing Technical Aspects practice questions
Practise PMP questions linked to Process — Managing Technical Aspects.
Business Environment — Strategy and Value practice questions
Practise PMP questions linked to Business Environment — Strategy and Value.
Business Environment: strategy and project benefits practice questions
Practise PMP questions linked to Business Environment: strategy and project benefits.
PMP fundamentals practice questions
Practise PMP questions linked to PMP fundamentals.
PMP scenario practice questions
Practise PMP questions linked to PMP scenario.
PMP troubleshooting practice questions
Practise PMP questions linked to PMP troubleshooting.
Practice this exam
Start a free PMP practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PMP question test?
Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Risk budget — The 'Plan Risk Management' process is the first step in risk management planning, and its primary output is the Risk Management Plan (Option C). This plan defines how risk management activities will be structured and performed throughout the project. The Risk Budget (Option A) is also an output of this process, as it allocates funds specifically for risk responses, including contingency reserves, based on the agreed risk thresholds and management approach.
What should I do if I get this PMP question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Last reviewed: Jun 11, 2026
This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.