- A
Create a detailed project schedule and assign tasks immediately
Why wrong: This does not address team norms.
- B
Facilitate a team charter workshop to collaboratively define ground rules, values, and communication protocols
A team charter sets expectations and fosters ownership.
- C
Ask each team member to submit a list of their personal expectations
Why wrong: Without synthesis, this may lead to confusion.
- D
Send an email listing team rules and ask for acknowledgment
Why wrong: This approach is top-down and less effective for buy-in.
Quick Answer
The answer is to facilitate a team charter workshop to collaboratively define ground rules, values, and communication protocols. This is correct because a team charter is the foundational document for building a high-performing team, as it formally establishes shared expectations for behavior, decision-making, and how the team will interact. By co-creating these guidelines, the project manager fosters ownership and alignment, which directly supports the Tuckman model’s transition from forming to norming. On the PMP exam, this question tests your understanding of the “Develop Team” process and the distinction between formal team-building tools and informal or vague approaches. A common trap is choosing an option that focuses only on technical skills or one that is too informal, like a simple email. Remember the memory tip: “Charter before character”—establish the rules of engagement before the team can perform.
PMP People — Leading Projects Practice Question
This PMP practice question tests your understanding of people — leading projects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
A project manager is forming a new project team. To build a high-performing team, the project manager wants to establish clear expectations for behavior and communication. What should the project manager do?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Facilitate a team charter workshop to collaboratively define ground rules, values, and communication protocols
Option A is correct because a team charter is a formal document that outlines team values, communication guidelines, and ground rules. It is a key tool for building a high-performing team. Option B is too informal. Option C focuses only on technical aspects. Option D is vague and does not provide clear guidelines.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Create a detailed project schedule and assign tasks immediately
Why it's wrong here
This does not address team norms.
- ✓
Facilitate a team charter workshop to collaboratively define ground rules, values, and communication protocols
Why this is correct
A team charter sets expectations and fosters ownership.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Ask each team member to submit a list of their personal expectations
Why it's wrong here
Without synthesis, this may lead to confusion.
- ✗
Send an email listing team rules and ask for acknowledgment
Why it's wrong here
This approach is top-down and less effective for buy-in.
Common exam traps
Common exam trap: answer the scenario, not the keyword
Many certification questions include familiar terms but test a specific constraint. Read the exact wording before choosing an answer that is generally true but wrong for this case.
Trap categories for this question
Similar concept trap
Without synthesis, this may lead to confusion.
Detailed technical explanation
How to think about this question
This question should be treated as a scenario, not a definition check. Identify the problem, the constraint and the best action. Then compare each option against those facts.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
- Use explanations to understand the rule behind the answer.
TExam Day Tips
- Underline the problem statement mentally.
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which PMP exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.
- →
People — Leading Projects — study guide chapter
Learn the concepts, then practise the questions
- →
People — Leading Projects practice questions
Targeted practice on this topic area only
- →
All PMP questions
892 questions across all exam domains
- →
Project Management Professional PMP study guide
Full concept coverage aligned to exam objectives
- →
PMP practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PMP practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
People — Leading Projects practice questions
Practise PMP questions linked to People — Leading Projects.
Process — Managing Technical Aspects practice questions
Practise PMP questions linked to Process — Managing Technical Aspects.
Business Environment — Strategy and Value practice questions
Practise PMP questions linked to Business Environment — Strategy and Value.
Business Environment: strategy and project benefits practice questions
Practise PMP questions linked to Business Environment: strategy and project benefits.
PMP fundamentals practice questions
Practise PMP questions linked to PMP fundamentals.
PMP scenario practice questions
Practise PMP questions linked to PMP scenario.
PMP troubleshooting practice questions
Practise PMP questions linked to PMP troubleshooting.
Practice this exam
Start a free PMP practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PMP question test?
People — Leading Projects — This question tests People — Leading Projects — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Facilitate a team charter workshop to collaboratively define ground rules, values, and communication protocols — Option A is correct because a team charter is a formal document that outlines team values, communication guidelines, and ground rules. It is a key tool for building a high-performing team. Option B is too informal. Option C focuses only on technical aspects. Option D is vague and does not provide clear guidelines.
What should I do if I get this PMP question wrong?
Identify which PMP exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Same concept, more angles
1 more ways this is tested on PMP
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. You are building a new project team for a complex initiative. To set the team up for success, you want to establish a high-performing team environment from the start. Which TWO actions should you take?
easy- ✓ A.Clearly define roles, responsibilities, and decision-making authority
- B.Assign team members to specific tasks immediately to ensure quick progress
- C.Conduct a team-building retreat after the first project milestone
- ✓ D.Facilitate a team kick-off workshop to create a team charter and establish norms
- E.Provide each team member with a copy of the project management plan
Why A: Options A and D are correct because involving the team in creating a team charter and defining clear roles and responsibilities are foundational for team performance. Option B is wrong as it's not a starting action. Option C is premature. Option E is not a typical PM action.
Last reviewed: Jun 21, 2026
This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.