Addressing Team Burnout: Empathetic Conversation vs. Budget Increase
A project manager discovers that a team member has been working overtime for weeks to meet a deadline. The team member appears stressed and burnt out. The project manager is concerned about the team member's well-being and the sustainability of the project. What should the project manager do?
Quick Answer
The correct answer is to schedule a private meeting to discuss the workload, express concern, and explore options for support or reprioritization. This choice is correct because it embodies the servant leadership mindset central to the PMP exam, which prioritizes team well-being and sustainable performance over rigid adherence to deadlines. When addressing team burnout from overtime, an empathetic conversation allows the project manager to uncover root causes—such as unrealistic scope or resource gaps—before jumping to solutions. On the PMP exam, this scenario tests your ability to apply the "Manage Team" process and the Agile principle of inspecting and adapting, with a common trap being the impulse to immediately request a budget increase, which may mask deeper issues like poor prioritization. Remember the memory tip: "Listen first, budget later"—empathy uncovers the real problem, while money only treats a symptom.
⚠ Common exam trap
Test-takers frequently choose Option B (directive stop) because it seems decisive, but the PMP exam emphasizes collaborative problem-solving over authoritarian commands, especially when team well-being is at stake.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Schedule a private meeting to discuss the workload, express concern, and explore options for support or reprioritization
It aligns with the PMP's focus on servant leadership and proactive stakeholder management. By scheduling a private meeting, the project manager demonstrates empathy, addresses the root cause of burnout, and collaboratively explores solutions like reprioritization or resource reallocation, which sustains both team well-being and project delivery.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Increase the project budget to hire additional help immediately
Why it's wrong here
A conversation should precede budget decisions.
- ✗
Warn the team member that overtime is not sustainable and require them to stop
Why it's wrong here
This is too directive and may not address underlying issues.
- ✗
Ignore the situation as long as deadlines are met
Why it's wrong here
Neglecting team well-being can lead to burnout.
- ✓
Schedule a private meeting to discuss the workload, express concern, and explore options for support or reprioritization
Why this is correct
Empathy and support align with servant leadership.
Go deeper
Related to this question
Learn chapter
Introduction to the PMP Exam and Project Management Basics
Key term
Project Management Plan
A formal, approved document that defines how a project is executed, monitored, controlled, and closed, serving as the single source of truth for the project team.
Key term
Training and Development
Training and Development is the process of enhancing team members' skills, knowledge, and competencies to improve project performance and achieve career growth.
About these practice questions
One of 800 original PMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
Same concept, more angles
1 more way this is tested on PMP
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. You are managing a project where the team has been working overtime for several weeks to meet a milestone. The milestone is achieved, but the team is exhausted. What should you do to sustain the team's performance?
easy- ✓ A.Conduct a retrospective to identify causes of overtime and implement improvements
- B.Reward the team with a bonus and move on to the next phase
- C.Encourage the team to take a few days off to recover
- D.Increase the team's resources for the next milestone
Why A: A retrospective directly addresses the root cause of unsustainable overtime, enabling the project manager to implement process improvements that prevent recurrence. Sustaining team performance requires addressing systemic issues, not just short-term relief. This aligns with the PMI talent triangle's emphasis on leadership and team motivation through continuous improvement.
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.