Courseiva
Process — Managing Technical AspectsmediumMultiple ChoiceObjective-mapped

CPI Below 1 and SPI Above 1 Often Indicate Crashing

A project manager notices that the project's cost performance index (CPI) is 0.8 and the schedule performance index (SPI) is 1.1. What is the MOST likely cause of this situation?

Quick Answer

The correct answer is crashing, because a CPI less than 1 and SPI greater than 1 directly point to a project that is ahead of schedule but over budget. A Cost Performance Index of 0.8 means you are earning only 80 cents for every dollar spent, indicating cost inefficiency, while a Schedule Performance Index of 1.1 shows you are completing 110% of planned work, meaning you are ahead of schedule. Crashing is a schedule compression technique that adds extra resources—often at higher cost—to critical path activities to gain time, which perfectly explains why you would see this specific metric combination. On the PMP exam, this scenario tests your ability to interpret earned value management (EVM) data and link it to real-world actions; a common trap is confusing crashing with fast-tracking, which does not increase cost. Remember the memory tip: “Crash costs cash, but speeds the dash”—when you see a low CPI paired with a high SPI, think of spending more money to buy back time.

⚠ Common exam trap

The trap here is that candidates often misinterpret CPI < 1 as 'behind schedule' and SPI > 1 as 'under budget,' confusing cost and schedule performance indices, or they fail to recognize crashing as the specific cause of this opposite-direction variance.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The project is ahead of schedule but over budget, possibly due to crashing.

A CPI of 0.8 indicates the project is over budget (earning only $0.80 for every $1.00 spent), while an SPI of 1.1 indicates it is ahead of schedule (completing 110% of planned work). Crashing is a schedule compression technique that adds resources to critical path activities, increasing cost to gain schedule performance, which directly explains this combination of metrics.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The project is ahead of schedule and under budget.

    Why it's wrong here

    CPI < 1 means over budget, not under.

  • The project is behind schedule and over budget.

    Why it's wrong here

    SPI > 1 means ahead of schedule.

  • The project is ahead of schedule but over budget, possibly due to crashing.

    Why this is correct

    Crashing adds cost to gain time, explaining the indices.

  • The project is behind schedule and under budget.

    Why it's wrong here

    SPI > 1 means ahead of schedule, not behind.

About these practice questions

One of 800 original PMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

2 more ways this is tested on PMP

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Your project's cost performance index (CPI) is 0.8, and the schedule performance index (SPI) is 1.1. The project is in the execution phase. What is the most likely reason for these indices?

easy
  • A.The team had to rework deliverables due to quality issues
  • B.The project is experiencing scope creep
  • C.The team is working more efficiently than planned
  • D.The project manager used crashing to meet a deadline, adding resources and increasing costs

Why D: A CPI of 0.8 indicates cost overrun (spending more than planned) while an SPI of 1.1 indicates the project is ahead of schedule (more work completed than planned). Crashing involves adding resources to critical path activities to compress the schedule, which increases costs (lower CPI) but can improve schedule performance (higher SPI). Option A is incorrect because rework due to quality issues would likely increase both cost and schedule, resulting in both CPI and SPI being less than 1. Option B is incorrect because scope creep typically increases both cost and schedule, not resulting in SPI > 1. Option C is incorrect because working more efficiently would likely improve both CPI and SPI, not lead to a cost overrun.

Variation 2. You are managing a project that has a cost performance index (CPI) of 0.8 and a schedule performance index (SPI) of 1.1. The project is behind schedule? The earned value data shows EV = $80,000, PV = $72,727, and AC = $100,000. Which THREE actions should you take?

hard
  • A.Analyze the cost variance to identify root causes, such as inefficiencies or inaccurate estimates
  • B.Reduce the project scope to cut costs
  • C.Implement schedule compression techniques like crashing to bring the schedule back on track
  • D.Validate that all work performed is within the approved scope and that no gold-plating has occurred
  • E.Review the work breakdown structure to ensure that all work packages are properly estimated

Why A: Options A, D, and E are correct. Since the CPI is 0.8 (cost overrun) and SPI is 1.1 (ahead of schedule), the focus should be on cost performance and scope validation. A: The cost variance (CV = EV - AC = -$20,000) is negative, so analyzing root causes of the cost overrun is necessary. D: With a cost overrun, it is important to ensure no gold-plating or unauthorized scope has been added, validating that all work performed is within the approved scope. E: Reviewing the WBS estimates helps identify if inaccuracies in estimating contributed to the cost overrun. Option B is incorrect because reducing scope unilaterally bypasses change control and could impact value. Option C is incorrect because schedule compression is not appropriate when the project is already ahead of schedule (SPI > 1).

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.