Which THREE of the following are Agile principles?
Trap 1: Agile processes should be as complex as possible
Simplicity is encouraged.
Trap 2: Maximize the amount of work not done
The principle is 'simplicity—the art of maximizing the amount of work not done—is essential'.
- A
Maintain a constant, sustainable development pace
This is a key principle.
- B
Welcome changing requirements, even late in development
This is a core principle.
- C
Our highest priority is to satisfy the customer
This is the first principle.
- D
Agile processes should be as complex as possible
Why it fails: Simplicity is encouraged.
- E
Maximize the amount of work not done
Why it fails: The principle is 'simplicity—the art of maximizing the amount of work not done—is essential'.