Delivery on the PMI-ACP exam covers how agile teams actually produce value: limiting work in progress, slicing features small, keeping flow steady, and re-aligning with organizational priorities. Questions are scenario-based, asking you to choose the first or most agile action when delivery breaks down, so you must reason about flow, feedback, and stakeholder alignment rather than recall definitions.

Courseiva uses original exam-style practice questions designed for learning and revision. The goal is to understand the concepts, recognise exam patterns, and improve through explanations — not memorise copied exam dumps.

Editorial oversight:Johnson Ajibi· MSc IT Security, IEEE Senior Member
20 questionsDomain: Delivery

What the exam tests

What to know about Delivery

You must be able to diagnose a delivery problem and pick the smallest agile corrective action: limit WIP, remove blockers, slice features smaller, and re-prioritize the backlog. The single most important thing is protecting flow and delivering value incrementally rather than adding capacity or pushing work through.

Applying Kanban WIP limits and managing blocked items without breaking the pull system

Slicing large features into smaller increments that deliver value sooner

Using flow metrics such as cycle time and throughput to expose delivery problems

Re-aligning delivered features with shifting organizational priorities through backlog refinement

Watch out for

Common Delivery exam traps

  • ▸Raising the WIP limit or pushing blocked work forward instead of addressing the blocker and restoring flow
  • ▸Choosing a big-bang release or full redesign when the agile answer is to slice smaller and deliver incrementally
  • ▸Escalating or blaming stakeholders before inspecting the backlog and re-prioritizing against current organizational goals

Practice set

Delivery questions

20 questions · select your answer, then reveal the explanation

Question 1easymultiple choice
Read the full Delivery explanation →

Which document is most important for defining the product vision?

Question 2hardmultiple choice
Read the full Delivery explanation →

The project stakeholders are unhappy because the delivered features do not align with the current organizational priorities. What should the practitioner do first?

Question 3easymultiple choice
Read the full Delivery explanation →

An agile team is coordinating tasks across multiple cross-functional teams. Which meeting is most effective for synchronizing dependencies?

Question 4mediummultiple choice
Read the full Delivery explanation →

During sprint planning, a team discovers that their velocity has decreased by 20% over the last two iterations. What should the team do first?

Question 5hardmulti select
Read the full Delivery explanation →

A team is coordinating releases across three different scrum teams working on the same product. Which THREE practices should be utilized?

Question 6hardmultiple choice
Read the full Delivery explanation →

An organization is moving from project-based to product-based funding. How should the agile practitioner advise the team to measure success?

Question 7mediummulti select
Read the full Delivery explanation →

A cross-functional team is experiencing long lead times for feature delivery. Which TWO actions would help optimize the end-to-end flow?

Question 8mediummultiple choice
Read the full Delivery explanation →

A team is struggling with frequent context switching during their sprint. Which lean technique should the practitioner implement to optimize end-to-end flow?

Question 9easymultiple choice
Read the full Delivery explanation →

A team is struggling to maintain a consistent cadence due to external dependencies. Which action best aligns with optimizing end-to-end flow?

Question 10easymultiple choice
Read the full Delivery explanation →

Which metric is most useful for measuring the team's ability to deliver consistent value per iteration?

Question 11hardmultiple choice
Read the full Delivery explanation →

A large agile project requires coordinating work across four teams. How should the practitioner handle dependency management?

Question 12mediummultiple choice
Read the full Delivery explanation →

During sprint planning, the team discovers they cannot complete a high-priority feature due to a technical blocker. What should the practitioner do?

Question 13mediummultiple choice
Read the full Delivery explanation →

A team is using cumulative flow diagrams to identify bottlenecks. The chart shows a widening gap between the 'In Progress' and 'Done' states. What does this indicate?

Question 14hardmultiple choice
Read the full Delivery explanation →

An organization is transitioning to agile but struggles with siloed teams. Which approach best optimizes the end-to-end flow of delivery?

Question 15easymultiple choice
Read the full Delivery explanation →

Which of the following is an effective way to prioritize a product backlog based on organizational goals?

Question 16mediummultiple choice
Read the full Delivery explanation →

A project is experiencing significant scope creep. How should the practitioner handle this to protect the team's delivery capacity?

Question 17hardmultiple choice
Read the full Delivery explanation →

A team's cycle time has significantly increased over three sprints. What is the most appropriate first step to identify the root cause?

Question 18easymultiple choice
Read the full Delivery explanation →

What is the primary purpose of a sprint review?

Question 19easymultiple choice
Read the full Delivery explanation →

What does a 'Definition of Done' ensure in an agile delivery?

Question 20easymultiple choice
Read the full Delivery explanation →

Which visual tool is best suited for identifying bottlenecks in a team's workflow?

Free account

Track your progress over time

Create a free account to save your results and see which topics improve across sessions.

Focused Delivery sessions

Start a Delivery only practice session

Every question in these sessions is drawn from the Delivery domain — nothing else.

Related practice questions

Related PMI-ACP topic practice pages

Move into related areas when this topic feels solid.

Frequently asked questions

What does the PMI-ACP exam test about Delivery?
You must be able to diagnose a delivery problem and pick the smallest agile corrective action: limit WIP, remove blockers, slice features smaller, and re-prioritize the backlog. The single most important thing is protecting flow and delivering value incrementally rather than adding capacity or pushing work through.
How should I use these practice questions?
Select your answer before revealing the explanation. Then read why each option is right or wrong — this active recall approach builds retention far faster than re-reading notes.
Can I practise just Delivery questions in a focused session?
Yes — the session launcher on this page draws every question from the Delivery domain. Use a 10-question session first to gauge your baseline, then move to 20 or 30 once the weak spots are clear.
Where can I practise other PMI-ACP topics?
Use the topic links above to move to related areas, or go back to the PMI-ACP question bank to see all topics.