PMI-ACP Leadership Practice Question
An agile team is having trouble getting feedback from a remote stakeholder. What should you do?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Facilitate a session to find a collaborative tool or meeting time that works for everyone.
Improving the communication channel is the responsibility of the agile leader to ensure transparency.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Stop the project until the stakeholder is available.
Why it's wrong here
Stopping the project is an extreme measure; seek to improve collaboration instead.
- ✓
Facilitate a session to find a collaborative tool or meeting time that works for everyone.
Why this is correct
Proactive facilitation ensures the team has the engagement they need.
- ✗
Send the stakeholder a daily summary of the work.
Why it's wrong here
Passive communication is not an effective substitute for active stakeholder engagement.
- ✗
Assume the stakeholder is not interested and proceed without them.
Why it's wrong here
Ignoring stakeholders risks building the wrong product.
About these practice questions
Courseiva writes every PMI-ACP question from scratch — 218 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official PMI exam blueprint
This PMI-ACP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMI-ACP exam.