PMI-ACP Mindset Practice Question
A stakeholder asks to change a completed feature. What is the correct response?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Evaluate the change's value and discuss the impact with the PO.
Welcoming change is an Agile principle, provided the change is evaluated for value and impact.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Evaluate the change's value and discuss the impact with the PO.
Why this is correct
This is the correct balance of agility and project control.
- ✗
Tell them it's too late.
Why it's wrong here
Agile embraces change.
- ✗
Charge the stakeholder for the rework.
Why it's wrong here
This is a transactional approach, not Agile.
- ✗
Do the change immediately without question.
Why it's wrong here
Changes need evaluation to ensure they add value.
About these practice questions
Courseiva writes every PMI-ACP question from scratch — 218 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official PMI exam blueprint
This PMI-ACP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMI-ACP exam.