PMI-ACP Delivery Practice Question
A large agile project requires coordinating work across four teams. How should the practitioner handle dependency management?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Require all teams to participate in a daily Scrum of Scrums.
Scrum of Scrums is a standard framework for cross-team coordination in agile at scale.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Require all teams to participate in a daily Scrum of Scrums.
Why this is correct
This allows teams to surface and resolve dependencies daily.
- ✗
Stop all work until the dependencies are resolved.
Why it's wrong here
This is not an agile approach to delivery.
- ✗
Assign a single manager to direct all four teams.
Why it's wrong here
This centralizes control and undermines self-organization.
- ✗
Merge all teams into one large team to simplify communication.
Why it's wrong here
Large teams are inefficient and violate the Scrum team size guidelines.
About these practice questions
One of 218 original PMI-ACP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official PMI exam blueprint
This PMI-ACP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMI-ACP exam.