Courseiva
PRINCE2 Practices →hardMultiple Choice

PRINCE2F PRINCE2 Practices Practice Question

Who typically authorizes the use of the change budget?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Project Board

The Project Board authorizes the change budget, but they may delegate authority to the Change Authority to approve changes within that budget.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Project Board

    Why this is correct

    The Project Board authorises use of the change budget, since it holds the overall project budget and tolerances. This satisfies the stem's requirement, as the Project Manager may only draw on it within delegated change tolerances.

  • ✗

    Project Manager

    Why it's wrong here

    The Project Manager administers the change budget day to day but does not hold the delegated authority to authorise its use. That authority sits with the Change Authority; the Project Manager would be the correct choice for recording and tracking change expenditure.

  • ✗

    Senior User

    Why it's wrong here

    The Senior User represents the interests of those who will use the project's products and is responsible for specifying user requirements and confirming benefits realisation. While they approve changes from a user perspective, their remit does not extend to authorizing the project's financial change budget. This financial accountability rests with the Executive, who holds the overall budget and is ultimately responsible for value for money, making them the correct authority for budget authorisation.

  • ✗

    Change Authority

    Why it's wrong here

    The Change Authority is a distinct role that may be delegated the change budget, but PRINCE2 places authorisation of change budget use with the Project Board, which owns the overall budget. The Change Authority would be correct only where the Board has formally delegated that authority.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.