Who is responsible for producing the Lessons Report at the end of the project?

⚠ Common exam trap

Watch out — candidates often confuse the responsibility for producing the Lessons Report with the responsibility for approving it or providing input, leading them to incorrectly select the Project Board or Senior User.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Project Manager

The Project Manager is responsible for producing the Lessons Report at the end of the project. This is because the Project Manager owns the day-to-day management of the project and is best positioned to capture and document lessons learned from the project's execution, ensuring that knowledge is transferred for future projects.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Project Support

    Why it's wrong here

    Project Support provides administrative and tooling assistance, such as maintaining the lessons log, but does not own the Lessons Report. It is tempting because support staff often draft documentation, yet PRINCE2 assigns accountability for producing this end-of-project management product to the Project Manager.

  • ✗

    Project Board

    Why it's wrong here

    The Project Board authorises the project and approves management products; it does not produce the Lessons Report. It is tempting because the Board reviews lessons and ensures they are passed on, but PRINCE2 places responsibility for creating the report with the Project Manager, who then submits it for approval.

  • ✓

    Project Manager

    Why this is correct

    The Project Manager produces the Lessons Report at the end of the project, as PRINCE2 assigns this responsibility to the role managing closure activities. This satisfies the stem's requirement for the end-of-project report, distinct from the Lessons Log, which is maintained throughout and reviewed at each stage boundary.

  • ✗

    Senior User

    Why it's wrong here

    The Senior User represents user interests and specifies requirements; the Lessons Report is a management product owned by the Project Manager. It is tempting because Senior Users contribute lessons from their business area, but accountability for compiling and logging lessons at project end sits with the Project Manager, not this role.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.