PRINCE2F PRINCE2 Practices Practice Question
Who is responsible for producing a Checkpoint Report?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Team Manager
Team Managers produce Checkpoint Reports to inform the Project Manager of progress against work packages.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Project Manager
Why it's wrong here
The PM produces Highlight Reports, not Checkpoint Reports.
- ✓
Team Manager
Why this is correct
Team Managers produce Checkpoint Reports.
- ✗
Senior User
Why it's wrong here
The Senior User does not produce Checkpoint Reports.
- ✗
Project Support
Why it's wrong here
Project Support may assist but is not responsible.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.