Who is responsible for ensuring that the products are delivered in accordance with the Work Package?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
The Team Manager
The Team Manager is responsible for accepting and delivering Work Packages, ensuring that products meet quality criteria.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
The Team Manager
Why this is correct
The Team Manager executes the Work Package and ensures products are delivered as defined.
- ✗
The Project Assurance
Why it's wrong here
Project Assurance monitors compliance but does not deliver products.
- ✗
The Senior Supplier
Why it's wrong here
The Senior Supplier is a Project Board role, not involved in day-to-day delivery.
- ✗
The Project Manager
Why it's wrong here
The Project Manager authorizes Work Packages but does not manage delivery.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.