PRINCE2F PRINCE2 Processes Practice Question
Who is responsible for ensuring that the products are delivered in accordance with the Work Package?
⚠ Common exam trap
The trap is confusing the Project Manager's responsibility for agreeing Work Packages with the Team Manager's responsibility for delivering the products within them.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
The Team Manager
In PRINCE2, the Team Manager is responsible for ensuring that the products assigned in a Work Package are delivered to the required quality and within the constraints agreed with the Project Manager. The Team Manager manages the team's work and reports progress.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
The Team Manager
Why this is correct
The Team Manager accepts the Work Package from the Project Manager and is accountable for its execution, directing the team to produce each product to the specified quality criteria and tolerances. This directly satisfies the stem's requirement: responsibility for delivery in accordance with the agreed Work Package sits with the Team Manager, not the Project Manager.
- ✗
The Project Assurance
Why it's wrong here
Project Assurance monitors the project independently on behalf of the Project Board, checking that roles, plans and controls are followed; it does not direct the work that produces the products. It tempts because assurance verifies compliance, which is correct when the question concerns independent oversight rather than delivery.
- ✗
The Senior Supplier
Why it's wrong here
The Senior Supplier provides supplier resources and agrees Work Package tolerances, but the Project Manager authorises the Work Package and confirms products meet its requirements. Tempting because suppliers do deliver products, yet accountability for delivery against the Work Package sits with the Project Manager.
- ✗
The Project Manager
Why it's wrong here
The Project Manager manages the team and reports progress, but the Work Package is agreed with the Team Manager, who then ensures delivery of its products to the specified quality criteria. It tempts because the Project Manager owns overall delivery, which is correct for tolerances and business case rather than Work Package execution.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed September 2026 · checked against the official PeopleCert exam blueprint
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.