PRINCE2 Practices →mediumMultiple Select

PRINCE2F PRINCE2 Practices Practice Question

Which THREE of the following are responsibilities of the Project Manager during the Managing a Stage Boundary process?

⚠ Common exam trap

PRINCE2 Foundation exam often tests the distinction between 'create' and 'approve' in PRINCE2 processes, so the trap here is confusing the Project Manager's role in creating the next Stage Plan with the Project Board's role in approving it.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Update the Business Case

In PRINCE2's Managing a Stage Boundary process, the Project Manager is responsible for updating the Business Case (option A) to confirm the project remains viable and aligned with the benefits, and for creating the next Stage Plan (option C) that will be submitted to the Project Board for approval. The Project Manager also produces the End Stage Report (option D), which summarizes stage performance and provides the basis for the board's decision to authorize the next stage. Option B is incorrect because the Project Plan is produced during Initiating a Project, not at each stage boundary. Option E is incorrect because approving the next Stage Plan is a Project Board decision, not a Project Manager responsibility.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Update the Business Case

    Why this is correct

    Updating the Business Case is a Project Manager responsibility in Managing a Stage Boundary, ensuring the justification reflects the stage's actual outcomes and the next stage's forecast. This satisfies the stem's requirement for Project Manager duties within that process.

  • ✗

    Produce the Project Plan

    Why it's wrong here

    The Project Plan is produced during Initiating a Project and updated in Controlling a Stage, not within Managing a Stage Boundary, where the next Stage Plan is created. It is tempting because the Project Manager owns the Project Plan, so its production feels like boundary work, but the process outputs stage-level plans.

  • ✓

    Create the next Stage Plan

    Why this is correct

    Creating the next Stage Plan is a Project Manager responsibility in Managing a Stage Boundary, producing the plan for the following stage so the Project Board can authorise it. This satisfies the stem's requirement for Project Manager duties within that process.

  • ✓

    Produce the End Stage Report

    Why this is correct

    Producing the End Stage Report is a Project Manager responsibility in Managing a Stage Boundary, summarising stage performance against plan and business case for the Project Board. This satisfies the stem's requirement for Project Manager duties within that process.

  • ✗

    Approve the next Stage Plan

    Why it's wrong here

    Approving the next Stage Plan is the Project Board's decision, taken after the Project Manager prepares it; the Project Manager authors and requests approval, never grants it. It is tempting because the Project Manager does assemble the plan, so the approval step appears adjacent, but authority to authorise sits above the project manager.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.