PRINCE2F PRINCE2 Processes Practice Question
Which THREE of the following are activities performed in the Closing a Project process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Produce the End Project Report
CP includes handing over products, producing the End Project Report, and recommending closure. Authorizing closure is done by the Board in DP; authorizing Work Packages is done in CS.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Produce the End Project Report
Why this is correct
The End Project Report is prepared in CP.
- ✓
Recommend project closure
Why this is correct
The Project Manager recommends closure in the End Project Report.
- ✓
Hand over products to the customer
Why this is correct
Product handover is a key activity in CP.
- ✗
Authorize project closure
Why it's wrong here
Authorization is done by the Project Board in DP.
- ✗
Authorize Work Packages
Why it's wrong here
Work Packages are authorized in CS.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
Same concept, more angles
2 more ways this is tested on PRINCE2F
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. Which process ensures that the project's products are formally accepted and the project is closed in a controlled way?
easy- ✓ A.Closing a Project
- B.Managing a Stage Boundary
- C.Controlling a Stage
- D.Directing a Project
Why A: Closing a Project ensures controlled closure, product handover, and lessons learned.
Variation 2. Which TWO of the following are typical activities in the Closing a Project process?
easy- A.Update the Project Brief
- B.Produce the End Stage Report
- C.Authorize the next stage
- ✓ D.Hand over the project's products to the operational environment
- ✓ E.Produce the Lessons Report
Why D: Closing a Project includes handing over products and producing the Lessons Report. The End Stage Report is from SB, and the Project Brief is from SU.
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.