Which role is responsible for providing assurance that the project is being managed correctly from a business perspective?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project Assurance
Project Assurance is independent of the Project Manager and reports to the Project Board. Business assurance is one aspect of Project Assurance.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Project Manager
Why it's wrong here
The Project Manager manages the project; assurance checks are independent.
- ✓
Project Assurance
Why this is correct
Project Assurance performs independent oversight on behalf of the Project Board.
- ✗
Team Manager
Why it's wrong here
The Team Manager is responsible for delivering work packages, not assurance.
- ✗
Project Support
Why it's wrong here
Project Support provides administrative assistance, not assurance.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.