Which role is responsible for providing assurance that the project is being managed correctly from a business perspective?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Project Assurance

Project Assurance is independent of the Project Manager and reports to the Project Board. Business assurance is one aspect of Project Assurance.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Project Manager

    Why it's wrong here

    The Project Manager runs the project day to day and cannot independently assure their own management. It is tempting because the role owns delivery, but assurance from a business perspective is provided by the Project Board's business assurance role, not the Project Manager.

  • ✓

    Project Assurance

    Why this is correct

    Project Assurance independently monitors all three stakeholder interests — business, user and supplier — on behalf of the Project Board. The business perspective specifically confirms the project remains justified and aligned with the Business Case, which is the assurance the stem demands.

  • ✗

    Team Manager

    Why it's wrong here

    The Team Manager manages product delivery for a team and reports progress, providing no business-perspective assurance. It is tempting because team managers supply status information, but business assurance rests with the Project Board's business assurance role, not the Team Manager.

  • ✗

    Project Support

    Why it's wrong here

    Project Support provides administrative and tooling assistance to the project management team, holding no assurance remit. It is tempting because support staff interact with governance artefacts, but business assurance belongs to the Project Board's business assurance role, not Project Support.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.