Which role is responsible for providing assurance that the project is being managed correctly from a business perspective?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project Assurance

Project Assurance is independent of the Project Manager and reports to the Project Board. Business assurance is one aspect of Project Assurance.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project Manager

    Why it's wrong here

    The Project Manager manages the project; assurance checks are independent.

  • Project Assurance

    Why this is correct

    Project Assurance performs independent oversight on behalf of the Project Board.

  • Team Manager

    Why it's wrong here

    The Team Manager is responsible for delivering work packages, not assurance.

  • Project Support

    Why it's wrong here

    Project Support provides administrative assistance, not assurance.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.