PRINCE2F Practice Question: Overview of PRINCE2 and the project environment
Which role is responsible for maintaining the Business Case throughout the project?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Senior Responsible Owner (Executive)
The Senior Responsible Owner (Executive) is accountable for the Business Case. Option B is correct. The Project Manager maintains the Business Case on a day-to-day basis but is not ultimately responsible. The Team Manager does not have this responsibility. The Change Authority is responsible for change decisions, not the Business Case.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Team Manager
Why it's wrong here
Team Managers are responsible for delivering work packages.
- ✓
Senior Responsible Owner (Executive)
Why this is correct
The Executive is responsible for the Business Case.
- ✗
Change Authority
Why it's wrong here
The Change Authority is responsible for change control decisions.
- ✗
Project Manager
Why it's wrong here
The Project Manager is responsible for day-to-day management of the project, but the Business Case is formally owned and maintained by the Senior User or Executive, as it requires ongoing validation of benefits and costs against organisational objectives. This option is tempting because the Project Manager does update the Business Case log and tracks deviations, leading one to assume ownership. In a scenario where the question asked who ensures the Business Case is kept under review and aligned with project progress, the Project Manager would be correct.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
Same concept, more angles
8 more ways this is tested on PRINCE2F
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. Which role is responsible for maintaining the Business Case throughout the project?
medium- A.Senior Supplier
- B.Senior User
- ✓ C.Executive
- D.Project Manager
Why C: The Executive (Senior Responsible Owner) owns the Business Case and is responsible for its maintenance.
Variation 2. Who is responsible for maintaining the Business Case throughout the project?
easy- A.The Project Manager
- B.The Senior Supplier
- ✓ C.The Executive
- D.The Senior User
Why C: The Executive is the project's senior responsible owner and has ultimate accountability for the Business Case. PRINCE2 explicitly assigns the Executive the responsibility for maintaining the Business Case throughout the project lifecycle, ensuring it remains viable and aligned with corporate objectives. The Project Manager manages the project on a day-to-day basis but does not own the Business Case.
Variation 3. Who is responsible for maintaining the Business Case throughout the project?
medium- A.Project Manager
- B.Senior User
- ✓ C.Executive
- D.Senior Supplier
Why C: The Executive (Senior Responsible Owner) owns the Business Case and is responsible for its maintenance.
Variation 4. Who is responsible for maintaining the Business Case throughout the project?
easy- A.Project Assurance
- B.Senior User
- C.Project Manager
- ✓ D.Executive (Senior Responsible Owner)
Variation 5. Who is responsible for maintaining the Business Case throughout the project?
medium- A.Project Manager
- B.Senior User
- ✓ C.Executive
- D.Senior Supplier
Why C: The Executive (Senior Responsible Owner) is the owner of the Business Case and is accountable for its development and maintenance. The Project Manager may assist in its creation but does not own it.
Variation 6. Who is responsible for maintaining the Business Case throughout the project?
easy- A.Project Assurance
- B.Senior User
- C.Executive
- ✓ D.Project Manager
Why D: Project Manager. According to PRINCE2, the Project Manager is responsible for the day-to-day maintenance of the Business Case, including updating it as necessary and ensuring it remains viable throughout the project. The Executive is ultimately accountable for the Business Case, but the Project Manager performs the actual maintenance activities.
Variation 7. Who is responsible for maintaining the Business Case throughout the project?
medium- A.The Executive
- ✓ B.The Project Manager
- C.The Project Support
- D.The Senior User
Why B: The Senior User is responsible for specifying the benefits and ensuring they are realized, but the Executive owns the Business Case. The Project Manager maintains it on a day-to-day basis.
Variation 8. Who is responsible for maintaining the Business Case throughout the project?
medium- A.Project Manager
- B.Senior User
- ✓ C.Executive
- D.Project Support
Why C: The Senior User represents the users and is responsible for ensuring the project delivers the required benefits; however, the Executive (Senior Responsible Owner) owns the Business Case. In PRINCE2, the Executive is ultimately accountable for the Business Case, but the Senior User provides input on benefits. The question asks who maintains it, and the correct answer is the Executive.
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.