Which report from the Team Manager is used by the Project Manager to review progress within a stage?

⚠ Common exam trap

PRINCE2F often tests the role-to-report mapping, so the trap is confusing the Team Manager's Checkpoint Report with the Project Manager's Highlight Report because both describe progress within a stage.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Checkpoint Report

The Checkpoint Report is the Team Manager's regular progress report to the Project Manager, produced at a frequency defined in the Work Package (often weekly or at agreed checkpoints). It summarizes progress, issues, and forecast against the Work Package, giving the Project Manager visibility within a stage. This is distinct from stage-level or project-board-level reports.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Highlight Report

    Why it's wrong here

    The Highlight Report is issued by the Project Manager to the Project Board, not by the Team Manager. It is tempting because it does summarise progress at regular intervals, but that reporting flows upward from the Project Manager, whereas the Team Manager's progress report to the Project Manager is the Checkpoint Report.

  • ✗

    End Stage Report

    Why it's wrong here

    The End Stage Report is created by the Project Manager at the conclusion of a stage, not by the Team Manager during it. It is tempting because it does address stage progress, but its timing and author are wrong; the Team Manager's regular progress report to the Project Manager is the Checkpoint Report.

  • ✗

    Exception Report

    Why it's wrong here

    An Exception Report is produced only when a stage or project is forecast to exceed its tolerances, so it cannot support routine progress review. It is tempting because it does inform the Project Manager of deviation, but it is event-driven escalation, not the regular Team Manager report used to review progress within a stage.

  • ✓

    Checkpoint Report

    Why this is correct

    The Checkpoint Report is the Team Manager's regular progress report to the Project Manager, covering work completed, work in progress and issues within the current stage. It directly satisfies the stem's requirement to review progress within a stage, feeding the Highlight Report cycle rather than end-stage reporting.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.