Courseiva
PRINCE2 ProcessesmediumMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

Which process is used by the Project Board to authorize the next stage of a project?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Directing a Project

The Project Board authorizes the next stage as part of Directing a Project, based on the End Stage Report and next Stage Plan from SB.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Managing a Stage Boundary

    Why it's wrong here

    SB produces the plan; Board authorizes in DP.

  • Starting Up a Project

    Why it's wrong here

    SU does not authorize stages; it's pre-project.

  • Directing a Project

    Why this is correct

    DP includes authorization of stage plans.

  • Controlling a Stage

    Why it's wrong here

    CS manages the current stage, not authorizes next.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.