Courseiva
PRINCE2 ProcesseseasyMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

Which process is responsible for authorizing the initiation of a project?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Directing a Project

Directing a Project (DP) is the process by which the Project Board authorizes initiation, stage plans, and project closure. Starting Up a Project (SU) prepares for initiation but does not authorize it.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Directing a Project

    Why this is correct

    DP includes the 'Authorize Initiation' activity, where the Project Board decides whether to proceed with initiation.

  • Controlling a Stage

    Why it's wrong here

    CS is for managing day-to-day work within a stage, not for authorizing initiation.

  • Starting Up a Project

    Why it's wrong here

    SU prepares the Project Brief and Stage Plan for initiation but does not authorize initiation.

  • Initiating a Project

    Why it's wrong here

    IP develops the PID but is itself authorized by the Project Board via DP.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

4 more ways this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Which process is responsible for authorizing the initiation of a project?

easy
  • A.Directing a Project
  • B.Controlling a Stage
  • C.Starting Up a Project
  • D.Initiating a Project

Why A: The 'Directing a Project' process is responsible for authorizing the initiation of a project because it is the decision-making layer where the Project Board reviews the Project Brief and decides whether to proceed. This process provides the key authorization for the project to move from the pre-project phase into the initiation stage, ensuring that the business case is viable and resources are committed.

Variation 2. Which process is responsible for authorizing the initiation of a project?

easy
  • A.Directing a Project
  • B.Starting Up a Project
  • C.Controlling a Stage
  • D.Initiating a Project

Why A: The Project Board, through the Directing a Project process, authorizes the initiation of a project after reviewing the outputs from Starting Up a Project.

Variation 3. Which process is responsible for authorizing the initiation of a project?

easy
  • A.Starting Up a Project
  • B.Controlling a Stage
  • C.Initiating a Project
  • D.Directing a Project

Why D: Directing a Project is the process by which the Project Board makes key decisions, including authorizing initiation. Starting Up a Project is a pre-project process that does not involve authorization.

Variation 4. Which process is responsible for authorizing the initiation of a project?

easy
  • A.Directing a Project
  • B.Initiating a Project
  • C.Starting Up a Project
  • D.Controlling a Stage

Why A: Directing a Project (DP) is the process where the Project Board makes key decisions, including authorizing initiation. Starting Up a Project (SU) prepares the conditions but does not authorize initiation.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.