PRINCE2 Practices →mediumMultiple Choice

PRINCE2F PRINCE2 Practices Practice Question

Which PRINCE2 plan provides the basis for day-to-day control by the Project Manager?

⚠ Common exam trap

A common trap is to select the Project Plan because it is the broadest plan, but PRINCE2 states that the Stage Plan is the basis for day-to-day control by the Project Manager.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Stage Plan

The Stage Plan is the correct answer because it provides the detailed, time-boxed plan for the current management stage, which the Project Manager uses for day-to-day control. PRINCE2 mandates that each stage has its own Stage Plan, derived from the Project Plan, and it includes the specific product descriptions, activities, and resource allocations needed for that stage. This plan is the basis for monitoring progress, managing issues, and making corrective decisions within the stage.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Stage Plan

    Why this is correct

    The Stage Plan covers one management stage and provides the day-to-day control baseline the Project Manager uses to monitor progress, authorise work and manage issues within that stage. It satisfies the requirement for the plan underpinning daily control.

  • ✗

    Exception Plan

    Why it's wrong here

    An Exception Plan covers recovery after a Stage Plan deviates beyond tolerance; it replaces the remainder of that plan once approved. Day-to-day control instead derives from the Stage Plan, which the Project Manager uses for routine monitoring and corrective action.

  • ✗

    Team Plan

    Why it's wrong here

    A Team Plan sits below the Stage Plan, produced by the Team Manager for a work package's products and resources. The Project Manager's day-to-day control uses the Stage Plan, against which progress and tolerances are monitored.

  • ✗

    Project Plan

    Why it's wrong here

    The Project Plan sits at project level, covering the whole project's products, schedule and tolerances; it underpins the Project Board's direction, not daily management. Day-to-day control comes from the Stage Plan, which the Project Manager owns.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.