Courseiva
PRINCE2 ProcesseshardMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

Which of the following correctly distinguishes Project Assurance from Project Support?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project Assurance is independent; Project Support provides administrative services

Project Assurance provides independent oversight and is accountable to the Project Board. Project Support provides administrative services to the Project Manager.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Both roles are performed by the same person in small projects

    Why it's wrong here

    While they can be combined, it does not distinguish them.

  • Project Support is independent; Project Assurance provides administrative services

    Why it's wrong here

    This is reversed.

  • Project Assurance is part of the Project Manager's team; Project Support is part of the Project Board

    Why it's wrong here

    Both roles are separate from the PM and Board.

  • Project Assurance is independent; Project Support provides administrative services

    Why this is correct

    Correct: Assurance is independent; Support is administrative.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Who is responsible for ensuring that project assurance is independent of the Project Manager?

hard
  • A.The Team Manager
  • B.The Project Manager
  • C.The Project Support
  • D.The Project Board

Why D: The Project Board is responsible for ensuring that project assurance is independent of the Project Manager. This is because the Project Board provides overall governance and oversight, and project assurance is a key function that must be objective and separate from the day-to-day management activities of the Project Manager. The PRINCE2 principle of 'defined roles and responsibilities' explicitly assigns this accountability to the Project Board to maintain the integrity of the assurance function.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.