PRINCE2 Practices →easyMultiple Choice

PRINCE2F PRINCE2 Practices Practice Question

What is the purpose of the Risk Register?

⚠ Common exam trap

A common mix-up: candidates confuse the Risk Register with the Risk Management Strategy or the Issue Register; candidates often think the Risk Register only lists threats or only the top risks, but PRINCE2 requires it to capture all risks (threats and opportunities) with full tracking details.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

To record and track all identified risks and their responses

The Risk Register is the central repository for recording and tracking all identified risks (both threats and opportunities) throughout the project lifecycle. It includes details such as risk description, probability, impact, proximity, and the planned responses, ensuring that every risk is managed and monitored. Option C is correct because it captures the complete purpose of the Risk Register as defined in PRINCE2.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    To list only the project's threats and their impacts

    Why it's wrong here

    The Risk Register records both threats and opportunities, along with their probability, impact, and responses. Listing only threats omits opportunities, which PRINCE2 explicitly manages. It is tempting because threats are the familiar focus, but the Register's purpose is comprehensive risk management across both categories.

  • ✗

    To document the top 10 risks for the Project Board

    Why it's wrong here

    The Risk Register captures all identified risks with their assessments and responses, not a fixed top ten for the Project Board. It is tempting because the Board reviews key risks, but that summary is produced from the Register, which holds the complete, dynamically updated risk information.

  • ✓

    To record and track all identified risks and their responses

    Why this is correct

    The Risk Register captures each identified risk, its cause, impact, probability, and the planned response, then tracks status throughout the project. This satisfies the purpose of recording and tracking all identified risks and their responses.

  • ✗

    To allocate the risk budget

    Why it's wrong here

    The Risk Register records identified risks, their probability, impact, proximity, and responses; it does not allocate budget. Budget allocation belongs to the risk budget within the Business Case. It is tempting because risk responses often require funding, but the Register documents and tracks risks, not finances.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.