What is the first step in the recommended risk management procedure?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Identify
The risk management procedure steps are: Identify, Assess, Plan, Implement, Communicate. Identify is first.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Implement
Why it's wrong here
Implement is the fourth step.
- ✗
Assess
Why it's wrong here
Assess is the second step.
- ✗
Plan
Why it's wrong here
Plan is the third step.
- ✓
Identify
Why this is correct
Identify is the first step in the risk management procedure.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.