Courseiva
PRINCE2 Practices →mediumMultiple Choice

PRINCE2F PRINCE2 Practices Practice Question

What is the first step in the recommended risk management procedure?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Identify

The risk management procedure steps are: Identify, Assess, Plan, Implement, Communicate. Identify is first.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Implement

    Why it's wrong here

    Implementation occurs near the end of the PRINCE2 risk management procedure, after risks have been identified, assessed and planned for. It is tempting because implementing responses is the visible outcome, but the procedure begins with Identify, and no response can be implemented before a risk is captured.

  • ✗

    Assess

    Why it's wrong here

    Assessment follows identification in PRINCE2's risk management procedure; you cannot assess a risk before it has been identified and recorded. It is tempting because assessment is the substantive analytical work, but the procedure's first step is Identify, which produces the risk register entries that assessment then evaluates.

  • ✗

    Plan

    Why it's wrong here

    Planning responses comes after identification and assessment in PRINCE2's risk management procedure, so it cannot be first. It is tempting because planning feels like the natural starting point for managing anything, but the procedure's initial step is Identify, which populates the risk register that planning then addresses.

  • ✓

    Identify

    Why this is correct

    Identifying risks comes first because the procedure must establish what could threaten the project before any assessment, planning or implementation can occur. PRINCE2's recommended sequence — identify, assess, plan, implement — makes this the necessary starting point, since later steps depend on a documented risk context to evaluate and respond to.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.