Project Board Responsibilities in PRINCE2
Which THREE of the following are typical responsibilities of the Project Board?
Quick Answer
The answer is approving the Project Initiation Documentation, along with monitoring progress via Highlight Reports and providing resources. These are typical responsibilities of the Project Board because the Board acts as the project’s senior decision-making body, ensuring the project remains viable and aligned with business objectives. The PID approval formalizes the project’s initiation, while reviewing Highlight Reports allows the Board to exercise control without micromanaging day-to-day work. On the PRINCE2 Foundation exam, this question tests your understanding of the Project Board’s strategic role versus the Project Manager’s tactical duties. A common trap is confusing Board responsibilities with those of the Project Manager, who prepares the PID but does not approve it. To remember, think of the Board as the “three pillars” of business, user, and supplier—each responsible for authorization, direction, and resource provision. A helpful mnemonic is “APR”: Approve PID, monitor Progress via reports, and provide Resources.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Providing resources and authorizing funding
The Project Board is responsible for overall project governance. They provide resources and authorize funding (A), monitor progress through Highlight Reports (B), and approve key documents such as the Project Initiation Documentation (D). Option C ('Managing day-to-day activities') is the responsibility of the Project Manager, not the Board. Option E ('Preparing the Business Case') is the responsibility of the Executive, not the Senior User or the Board collectively, though the Board may approve it.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Providing resources and authorizing funding
Why this is correct
The Project Board provides resources.
- ✓
Monitoring progress via Highlight Reports
Why this is correct
The Project Board receives Highlight Reports.
- ✗
Managing the day-to-day activities of the project
Why it's wrong here
That is the Project Manager's role.
- ✓
Approving the Project Initiation Documentation
Why this is correct
The Project Board approves the PID.
- ✗
Preparing the Business Case
Why it's wrong here
The Executive prepares the Business Case, not the whole Board.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
Same concept, more angles
3 more ways this is tested on PRINCE2F
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. Which THREE of the following are responsibilities of the Project Board?
hard- ✓ A.Providing overall direction and control
- B.Managing risks on a daily basis
- ✓ C.Approving the Project Plan
- D.Producing Highlight Reports
- ✓ E.Ensuring project assurance is carried out
Why A: The Project Board is responsible for providing overall direction and control of the project, ensuring it remains aligned with business objectives and governance requirements. This includes making key decisions, approving major deliverables, and authorizing stage transitions as defined in PRINCE2's management by stages principle.
Variation 2. Which THREE of the following are responsibilities of the Project Board?
hard- ✓ A.Providing overall direction and control of the project
- ✓ B.Approving the Project Plan and any Exception Plans
- ✓ C.Authorizing deviations from stage tolerances
- D.Maintaining the configuration management plan
- E.Reviewing the detailed quality of each product
Why A: The Project Board provides direction, approves plans, and authorizes deviations. Detailed review of products is not a Board responsibility; that is done by quality review. The configuration management plan is part of the project's management approach and is approved by the Board but not 'maintained' by them.
Variation 3. Which THREE of the following are responsibilities of the Project Board?
hard- A.Performing project assurance activities
- ✓ B.Making decisions on exception situations
- ✓ C.Approving stage plans
- D.Managing day-to-day activities
- ✓ E.Providing overall direction and control
Why B: The Project Board is accountable for the project's success, approves stage plans, and provides direction. The PM manages day-to-day, and assurance is delegated.
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.