Courseiva
People: organizations, teams, and leadershiphardMultiple ChoiceObjective-mapped

PRINCE2F People: organizations, teams, and leadership Practice Question

Exhibit

Refer to the exhibit.

Project Board Roles:
- Executive: Jane Doe
- Senior User: Bob Smith
- Senior Supplier: Acme Corp (represented by Alice Johnson)

Excerpt from the Communication Management Approach:
- Frequency of progress reports: weekly
- Escalation path: team -> project manager -> project board
- Project board decisions: by majority vote

The project board decides to use majority voting for all decisions. What is a potential issue with this decision-making process?

⚠ Common exam trap

PeopleCert often tests the misconception that majority voting is a valid decision-making method in PRINCE2, when in fact it violates the principle of unified direction and collective responsibility.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Using majority vote may undermine the principle of unified direction

PRINCE2's principle of 'continued business justification' and the requirement for unified direction mandate that the project board make decisions by consensus, not by majority vote. The project board represents business, user, and supplier interests as a single cohesive unit; majority voting would risk dividing the board and undermining the principle of unified direction, as it could allow one interest to override others without full agreement.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Using majority vote may undermine the principle of unified direction

    Why this is correct

    PRINCE2 recommends consensus, not majority vote.

  • Progress reports are too frequent, causing information overload

    Why it's wrong here

    Weekly reporting is typical.

  • The Senior Supplier is represented by an individual rather than the organization

    Why it's wrong here

    Representation is acceptable.

  • The roles are filled by three individuals, but there should be only two

    Why it's wrong here

    Three roles are standard.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.