During the Controlling a Stage process, the Project Manager receives a Checkpoint Report. Who prepared this report?
⚠ Common exam trap
PRINCE2 often tests the distinction between who prepares versus who receives reports; the trap here is confusing the Project Manager as the author of all reports, when in fact the Checkpoint Report is specifically authored by the Team Manager.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Team Manager
In PRINCE2, the Checkpoint Report is a progress report prepared by the Team Manager on behalf of the team. It provides the Project Manager with a snapshot of the work completed, planned, and any issues or risks within a work package. The Project Manager uses this report during the Controlling a Stage process to monitor progress and make informed decisions.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.