During the Controlling a Stage process, the Project Manager receives a Checkpoint Report. Who prepared this report?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The Team Manager

Checkpoint Reports are prepared by the Team Manager and sent to the Project Manager.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The Senior Supplier

    Why it's wrong here

    Senior Supplier is a Project Board role.

  • The Project Support

    Why it's wrong here

    Project Support may assist but does not prepare Checkpoint Reports.

  • The Team Manager

    Why this is correct

    Team Manager prepares Checkpoint Reports in MP.

  • The Project Board

    Why it's wrong here

    Board receives Highlight Reports, not Checkpoint Reports.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.