PRINCE2F PRINCE2 Processes Practice Question
During the Controlling a Stage process, the Project Manager receives a Checkpoint Report. Who prepared this report?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
The Team Manager
Checkpoint Reports are prepared by the Team Manager and sent to the Project Manager.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
The Senior Supplier
Why it's wrong here
Senior Supplier is a Project Board role.
- ✗
The Project Support
Why it's wrong here
Project Support may assist but does not prepare Checkpoint Reports.
- ✓
The Team Manager
Why this is correct
Team Manager prepares Checkpoint Reports in MP.
- ✗
The Project Board
Why it's wrong here
Board receives Highlight Reports, not Checkpoint Reports.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.