PRINCE2 Processes →hardMultiple Choice

PRINCE2F PRINCE2 Processes Practice Question

During the Controlling a Stage process, the Project Manager identifies a deviation that is expected to remain within the stage tolerance. What should the Project Manager do?

⚠ Common exam trap

PRINCE2F often tests the threshold between stage tolerance and exception, confusing candidates into escalating issues that are still within the Project Manager's delegated authority.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Take corrective action and continue

In PRINCE2, during the Controlling a Stage process, the Project Manager is responsible for monitoring work and taking corrective action if deviations occur. If the deviation is expected to remain within the stage tolerance, the Project Manager has the authority to take corrective action without escalating to the Project Board. The Project Board is only informed via Highlight Reports, but no exception is raised because the tolerance is not exceeded. Therefore, taking corrective action and continuing is the correct action.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Take corrective action and continue

    Why this is correct

    Stage tolerance delegates authority to the Project Manager, so a deviation contained within it needs no escalation to the Project Board. Corrective action restores performance against the Stage Plan while work continues, keeping the stage on track without invoking exception reporting.

  • ✗

    Inform the Project Board in the next Highlight Report

    Why it's wrong here

    Highlight Reports are progress updates sent to the Project Board, not a mechanism for seeking a tolerance decision. Since the deviation remains within stage tolerance, the Project Manager acts without board involvement; board escalation belongs to an Exception Report when tolerance is forecast to be exceeded.

  • ✗

    Raise an Exception Report to the Project Board

    Why it's wrong here

    An Exception Report is raised only when a deviation is forecast to breach stage tolerance, transferring the decision to the Project Board. Here the deviation stays within tolerance, so the Project Manager retains authority and records it in the Issue Register, taking corrective action within the stage plan.

  • ✗

    Escalate the issue to the Team Manager

    Why it's wrong here

    The Team Manager manages work packages and reports progress to the Project Manager; escalation runs upward, not downward, and stage-level tolerance sits with the Project Manager. A within-tolerance deviation is handled by the Project Manager directly, recording it and adjusting the stage plan.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.