PRINCE2F PRINCE2 Practices Practice Question
During the Closing a Project process, which report is used to evaluate the project's performance against the approved Business Case?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
End Project Report
The End Project Report is used to evaluate the project's performance against the Business Case and provide lessons for future projects.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
End Stage Report
Why it's wrong here
End Stage Reports are used during stage boundaries, not at project closure.
- ✗
Lessons Report
Why it's wrong here
The Lessons Report is a separate document that captures lessons learned.
- ✗
Benefits Review Plan
Why it's wrong here
The Benefits Review Plan defines when and how benefits will be measured, but is not a closure report.
- ✓
End Project Report
Why this is correct
The End Project Report reviews overall project performance against the Business Case.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.