During the Closing a Project process, which report is used to evaluate the project's performance against the approved Business Case?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

End Project Report

The End Project Report is used to evaluate the project's performance against the Business Case and provide lessons for future projects.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • End Stage Report

    Why it's wrong here

    End Stage Reports are used during stage boundaries, not at project closure.

  • Lessons Report

    Why it's wrong here

    The Lessons Report is a separate document that captures lessons learned.

  • Benefits Review Plan

    Why it's wrong here

    The Benefits Review Plan defines when and how benefits will be measured, but is not a closure report.

  • End Project Report

    Why this is correct

    The End Project Report reviews overall project performance against the Business Case.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.