Courseiva
PRINCE2 Processes →mediumMultiple Choice

PRINCE2F PRINCE2 Processes Practice Question

During a stage, the Project Manager needs to authorise a new body of work to a Team Manager, specifying the products, tolerances, and reporting requirements. Which PRINCE2 product is used for this authorisation?

⚠ Common exam trap

The trap here is treating the Team Plan or Stage Plan as the authorisation instrument, when the Work Package is what formally assigns and controls the delegated work.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Work Package

The Work Package is the formal agreement authorising a Team Manager to produce defined products within agreed tolerances and reporting requirements. A Stage Plan operates at the management-stage level, a Team Plan is the Team Manager's own detailed plan, and a Product Description covers only a single product. Only the Work Package bundles the scope, tolerances, and reporting needed for delegated authorisation.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Stage Plan

    Why it's wrong here

    A Stage Plan is produced by the Project Manager and approved by the Project Board to cover an entire management stage. It provides the overall scope, cost, and time baseline for the stage but is not the mechanism for authorising individual work packages to a Team Manager, so it is a level too high for this purpose.

  • ✓

    Work Package

    Why this is correct

    A Work Package is the agreement between the Project Manager and the Team Manager that authorises a defined set of products to be produced within stated tolerances. It includes the product descriptions, quality criteria, constraints, and reporting requirements, making it the correct instrument for assigning and controlling delegated work during a stage.

  • ✗

    Team Plan

    Why it's wrong here

    A Team Plan is optional and is produced by the Team Manager to show how the work package will be delivered at a detailed level. It is an output of accepting a work package, not the authorisation itself, so it cannot be the instrument the Project Manager uses to assign the work.

  • ✗

    Product Description

    Why it's wrong here

    A Product Description defines the purpose, composition, quality criteria, and quality method for a single product. It is referenced within a Work Package but does not itself authorise work or carry tolerances and reporting requirements, so it is too narrow to serve as the authorisation mechanism.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.