PRINCE2F Business Case and Organizing Practice Question

During a project, the Senior User reports that a key benefit is no longer achievable due to a change in market conditions. The project manager needs to update the Business Case. Which role is responsible for ensuring that the Business Case reflects the changed benefits?

⚠ Common exam trap

The trap here is assuming that the Senior User updates the Business Case because they are responsible for benefits, but in PRINCE2 the Project Manager maintains the document.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Project Manager

The Project Manager is responsible for updating the Business Case when changes occur, such as a key benefit becoming unachievable. They gather input from the Senior User and other stakeholders, revise the document, and present it to the Project Board for approval. The Senior User specifies benefits but does not update the Business Case. The Project Board and Executive approve but do not update it. This ensures the Business Case remains a accurate reflection of the project's viability.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Project Board

    Why it's wrong here

    The Project Board approves the Business Case but does not update it. Their role is to review the updated Business Case and decide whether to continue with the project. The Project Manager is responsible for the actual revision of the document. The Board's decision is based on the information provided by the Project Manager, ensuring that the project remains aligned with business objectives.

  • ✓

    Project Manager

    Why this is correct

    The Project Manager is responsible for updating the Business Case to reflect changes in benefits, costs, risks, or timescales. They gather information from stakeholders, including the Senior User, and revise the document accordingly. The Project Manager ensures that the Business Case remains accurate and up-to-date, providing the Project Board with the necessary information to make informed decisions about the project's continuation.

  • ✗

    Senior User

    Why it's wrong here

    The Senior User is responsible for specifying the benefits and ensuring they are realized, but they do not update the Business Case. Their role is to provide information about benefit realization and any changes that may affect it. The Project Manager is the one who consolidates this information into the Business Case. The Senior User's focus is on the user perspective, not the document itself.

  • ✗

    Executive

    Why it's wrong here

    The Executive is accountable for the Business Case and ensures it aligns with corporate strategy, but they do not personally update it. The Project Manager is tasked with maintaining the Business Case. The Executive's role is to provide direction and make decisions based on the updated information. The responsibility for the document's content lies with the Project Manager.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.