PRINCE2F People: organizations, teams, and leadership Practice Question

During a project, the Project Board has delegated change authority to a Change Authority for low-impact changes. A team member raises a Request for Change (RFC) that affects a product's scope and is assessed as low impact. Who should decide whether to approve this RFC?

⚠ Common exam trap

The trap here is assuming that the Project Board always decides on changes, ignoring the possibility of delegated change authority.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Change Authority

The Change Authority is the correct role to decide on low-impact changes when the Project Board has delegated that authority. The Project Manager assesses the change but does not decide, and the Project Board only gets involved if the change exceeds the delegated limits.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Project Board

    Why it's wrong here

    The Project Board retains overall accountability for changes, but it can delegate authority to a Change Authority. Since the RFC is low impact and authority has been delegated, the Project Board should not be involved in this decision.

  • ✗

    Project Manager

    Why it's wrong here

    The Project Manager is responsible for assessing the impact of the RFC and preparing it for decision, but if change authority has been delegated to a Change Authority for low-impact changes, the Project Manager should refer the decision to the Change Authority, not decide themselves.

  • ✗

    Senior User

    Why it's wrong here

    The Senior User is a member of the Project Board and represents user interests, but they do not have the authority to approve changes unless specifically delegated. In this case, the Change Authority has been given that authority for low-impact changes.

  • ✓

    Change Authority

    Why this is correct

    When the Project Board delegates change authority to a Change Authority for certain types of changes, such as low-impact ones, the Change Authority is responsible for approving or rejecting those changes. In this scenario, the RFC is low impact, so the Change Authority should decide.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.